Los Angeles City Council District 2: ADU permit timelines
Across 3,537 issued Accessory Dwelling Unit permits in Council District 2, applications averaged 170 calendar days (20 days shorter than the Los Angeles citywide average of 190 days), with 62% exceeding California’s 60-day review window under Gov. Code § 66317.
- 28,241 total LADBS permits in area
- 3,537 issued ADUs
- 2,196 ADUs over 60 days
- Updated Nov 14, 2026
See Adrin Nazarian’s official record
Computed from City of Los Angeles Department of Building and Safety (LADBS) submittal and issuance dates in Los Angeles Open Data.
From City of Los Angeles Open Data (LADBS), as of November 14, 2026.
- Issued ADUs measured
- 3,537
- Average wait
- 170 days
- Over 60-day statutory window
- 62%
- Declared ADU valuation
- $234.1 million
Elected representative for this district
Los Angeles City Council members oversee citywide housing policy, departmental budgets, and constituent permitting escalations for their district.
Recent ADU permit filings in Council District 2
The 15 most recently submitted Accessory Dwelling Unit filings recorded by LADBS in Council District 2. You can select any filing below to calculate its 60-day statutory deadline and prepare a written status request.
| Permit number | Address | Submitted | Status | Elapsed | Declared value |
|---|---|---|---|---|---|
| 25010-30002-01479supplemental permit to 25010-30000-01479 for changes to architectural plans | 11215-11215 1/2 W CALIFA STZone RD2-1 | Nov 13, 2026 | Issued | 0 days | $2,501 |
| 25010-30002-01480supplemental permit to 25010-30000-01480 for changes to architectural plans | 11217 W CALIFA STZone RD2-1 | Nov 13, 2026 | Issued | 0 days | $2,501 |
| 25014-20001-03266SUPPLEMENTAL PERMIT FOR 25014-20000-03266 TO INCREASE HEIGHT FROM 21'-6" TO 22'-10" | 6618 N GENTRY AVEZone R1-1 | Nov 10, 2026 | Issued | 0 days | $2,500 |
| 26014-20001-03028SUPPL. PERMIT TO 26014-20000-03028. REVISE DEMO AND PROPOSED FLOOR PLAN. REPLACE ROOF FRAMING AND RAISE CEILING HEIGHT. | 12626 W KITTRIDGE STZone R1-1 | Oct 30, 2026 | Issued | 0 days | $2,501 |
| 21014-20001-00551SUPPLEMENTAL PERMIT TO 21014-20000-00551 TO REVISE THE SCOPE OF WORK TO CONVERSION AND ADDITION TO DETACHED GARAGE TO CONVERT IT TO NEW ADU WITH ATTACHED ADU. RECONFIGURE APPROVED | 6306 N AGNES AVEZone R1-1 | Oct 29, 2026 | Issued | 0 days | $2,501 |
| 23010-20001-03658SUPPL. PERMIT TO 23010-20000-03658 TO REMOVE THE SOLAR PANELS. | 6711 N KATHERINE AVEZone R1-1-HPOZ | Oct 28, 2026 | Issued | 0 days | $2,501 |
| 25014-20001-00903EPLANSupplemental Permit to 25014-20000-00903 to Revise the Foundation Design and Column pads.NO CHANGE ON BUILDING DIM NOR LOCATION | 11492 W ALBERS STZone RD1.5-1VL | Oct 21, 2026 | Issued | 5 days | $5,000 |
| 26014-20001-02313SUPPLEMENTAL PERMIT TO 26014-20000-02313 TO REVISE THE FOUNDATION PLANS AND FOOTING DETAILS OF THE EXISTING PORTION OF BUILDING | 4354 N CAMELLIA AVEZone R1-1-RIO | Oct 21, 2026 | Issued | 0 days | $2,501 |
| 24010-30005-01979Supplemental permit to 24010-30000-01979 to revise the scope of work to " New 3-story Duplex B with attached ADU and attached Garage per ordinace LAMC 12.22 A.33 (c) and (e) | 5637-5637 1/2 N FULCHER AVEZone RD1.5-1VL | Oct 21, 2026 | Permit Finaled | 0 days | — |
| 25014-20002-03168SUPPL. PERMIT TO 25014-20000-03168 TO ADD NFPA13-D FIRE SPRINKLERS THROUGH OUT. | 13548 W BASSETT STZone R1-1 | Oct 20, 2026 | Issued | 0 days | $2,501 |
| 23010-10002-00515Supplemental permit to 23010-20000-00515 to (1) correct error in Bldg B (10422-10424 W Addison St) RFA calculation on A-00 cover sheet with no change in building design/layout/ dim | 10422-10424 W ADDISON STZone R1-1 | Oct 19, 2026 | Issued | 0 days | — |
| 26016-20002-08848[ePlan] SUPPLEMENTAL TO 26016-20000-08848 TO CAPTURE CORRECT OCCUPANCY AREA - CAPTURE SCHOOL FEE AREA | 6352 N COSTELLO AVEZone [Q]RD1.5-1 | Oct 15, 2026 | Permit Finaled | 0 days | — |
| 26014-20000-03930ADDITION TO AND CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 66323(A)(2) | 12825 W MIRANDA PLZone R1-1 | Oct 14, 2026 | Issued | 9 days | $50,000 |
| 25016-20001-33294SUPPLEMENTAL TO PERMIT 25016-20000-33294:REVISE INTERIOR LAYOUT AT BATHROOM AND LIVING/KITCHEN/DINNING AREA, (E) LAUNDRY TO REMIAN, (E) SHEAR WALLS AND OPENINGS TO REMAIN. NO CHAN | 1115 W LEADWELL STZone R1-1 | Oct 14, 2026 | Issued | 5 days | $10,000 |
| 25014-20001-03171eplan. Supplemental permit to 25014-20000-03171 to replace metal siding w/ cement board siding for ADU | 6021 N CARPENTER AVEZone R1-1 | Oct 7, 2026 | Permit Finaled | 19 days | — |
Check a Los Angeles building permit live
Search any permit number or street address in the City of Los Angeles Open Data registry. Your address stays in this browser tab and is never added to a link or stored.
60-day ADU shot-clock calculator & written notice
California Government Code § 66317 gives local permitting agencies 60 calendar days to ministerially approve or deny a complete Accessory Dwelling Unit application. Enter your application details below to calculate your statutory deadline and assemble a plain written status request for Los Angeles City Council District 2.
- Submittal date
- November 23, 2026
- Day 45 check-in
- January 7, 2027
- Day 60 statutory deadline
- January 22, 2027
- Current status
- 60 days remaining in the 60-day window
Review written notice to LADBS Plan Check Supervisor
November 23, 2026
To: Plan Check Supervisor
Los Angeles Department of Building and Safety (LADBS)
201 N. Figueroa Street, Los Angeles, CA 90012
CC: Office of Los Angeles City Council District 2 (Adrin Nazarian); California Department of Housing and Community Development (HCD) Housing Accountability Unit
Subject: Request for Ministerial ADU Review Status & Consolidated Corrections Under CA Gov. Code § 66317 — Permit #[PERMIT APPLICATION NUMBER]
Dear Plan Check Supervisor,
I am writing regarding Accessory Dwelling Unit (ADU) Permit Application #[PERMIT APPLICATION NUMBER] for [PROPERTY STREET ADDRESS, LOS ANGELES, CA], submitted on November 23, 2026.
Under California Government Code § 66317, the 60-day ministerial review window for a complete ADU application runs through January 22, 2027.
Pursuant to California Government Code § 66317, I respectfully request:
1. Immediate ministerial approval of this complete ADU application, OR
2. A single, complete, written set of objective code comments citing the exact code section for every remaining item so that all corrections can be resolved without serial plan-check cycles.
Please respond in writing with the current plan-check status, assigned plan checker, and next action date.
Sincerely,
[YOUR FULL NAME]
Permit Reference: #[PERMIT APPLICATION NUMBER]
Property Address: [PROPERTY STREET ADDRESS, LOS ANGELES, CA]
Election.org publishes official City of Los Angeles permit data and California statutory references for public accountability and citizen self-help. This draft is informational and is not legal representation; review every detail before sending.
Other Los Angeles Council districts
- Adrin Nazarian — City Council District 2Official officeholder record, term dates, and source roster.
- Los Angeles City Council District 1968 issued ADUs · 262 days average · 70% over 60 days
- Los Angeles City Council District 33,029 issued ADUs · 162 days average · 63% over 60 days
- Los Angeles City Council District 42,778 issued ADUs · 178 days average · 63% over 60 days
- Los Angeles City Council District 52,638 issued ADUs · 189 days average · 68% over 60 days
- Los Angeles City Council District 62,587 issued ADUs · 170 days average · 63% over 60 days
Up: All Los Angeles permit timelines, Los Angeles officials, Local government
Sources & notes
Permit registryCity of Los Angeles Department of Building and Safety (LADBS) via City of Los Angeles Open Data
Open data endpointdata.lacity.org/resource/pi9x-tg5x.json
StatuteCalifornia Government Code § 66317 (60-day ministerial ADU review)
Data updatedNov 14, 2026