Los Angeles building and ADU permit timelines
Every issued Accessory Dwelling Unit permit in City of Los Angeles Open Data measured against California’s 60-day ministerial review law (Gov. Code § 66317), joined to each sitting City Council member.
- 424,349 LADBS permits analyzed
- 36,027 issued ADUs
- 15 Council districts and 33 neighborhoods
- LADBS data updated Nov 14, 2026
See all Los Angeles elected officials
Figures are calculated directly from official City of Los Angeles Open Data (LADBS pi9x-tg5x) from submittal date to issue date. Election.org reports measured timelines and does not grade or endorse officeholders.
From City of Los Angeles Open Data (LADBS), as of November 14, 2026.
- Issued ADUs measured
- 36,027
- Citywide average wait
- 190 days
- Over 60-day statutory window
- 66%
- Declared ADU valuation
- $2.37 billion
All 15 Los Angeles City Council districts
Ordered from longest to shortest average wait between submittal and permit issuance. Across the latest 250 issued ADUs citywide, the median wait was 102 days and the 90th percentile was 410 days.
| District | Current council member | Issued ADUs | Average wait | Over 60-day law | Declared ADU value |
|---|---|---|---|---|---|
| Council District 1 | Not listed | 968 | 262 days | 70% | $68.1M |
| Council District 15 | Not listed | 1,304 | 246 days | 72% | $93.0M |
| Council District 14 | Not listed | 1,489 | 225 days | 72% | $99.7M |
| Council District 9 | Not listed | 1,455 | 217 days | 70% | $117.7M |
| Council District 8 | Not listed | 3,065 | 209 days | 68% | $202.0M |
| Council District 10 | Not listed | 2,614 | 204 days | 69% | $166.2M |
| Council District 11 | Not listed | 2,869 | 195 days | 69% | $204.1M |
| Council District 5 | Not listed | 2,638 | 189 days | 68% | $152.8M |
| Council District 7 | Not listed | 2,828 | 189 days | 65% | $184.7M |
| Council District 13 | Not listed | 1,795 | 186 days | 64% | $113.5M |
| Council District 4 | Not listed | 2,778 | 178 days | 63% | $166.5M |
| Council District 2 | Not listed | 3,537 | 170 days | 62% | $234.1M |
| Council District 6 | Not listed | 2,587 | 170 days | 63% | $166.6M |
| Council District 12 | Not listed | 3,071 | 166 days | 61% | $207.1M |
| Council District 3 | Not listed | 3,029 | 162 days | 63% | $190.4M |
33 Los Angeles Community Plan Areas
Neighborhood-level LADBS permit records ordered by issued ADU volume. Select any area to inspect its recent filings and statutory wait-time comparison.
| Community plan area | Issued ADUs | Average wait | Over 60-day law | Declared ADU value |
|---|---|---|---|---|
| West Adams – Baldwin Hills – Leimert | 2,613 | 204 days | 67% | $159.5M |
| South Los Angeles | 2,603 | 217 days | 72% | $188.5M |
| Northeast Los Angeles | 2,334 | 229 days | 69% | $146.7M |
| Wilshire | 2,286 | 197 days | 68% | $132.5M |
| Reseda – West Van Nuys | 2,025 | 155 days | 63% | $125.5M |
| Canoga Park – West Hills – Winnetka – Woodland Hills | 2,021 | 155 days | 60% | $125.4M |
| North Hollywood – Valley Village | 1,890 | 171 days | 61% | $123.8M |
| Van Nuys – North Sherman Oaks | 1,825 | 155 days | 61% | $121.2M |
| Southeast Los Angeles | 1,674 | 216 days | 69% | $126.9M |
| Sun Valley – La Tuna Canyon | 1,598 | 178 days | 62% | $112.2M |
| Palms – Mar Vista – Del Rey | 1,146 | 177 days | 70% | $70.8M |
| Mission Hills – Panorama City – North Hills | 1,138 | 170 days | 62% | $70.9M |
Show the other 21 Community Plan Areas
| Community plan area | Issued ADUs | Average wait | Over 60-day law | Declared ADU value |
|---|---|---|---|---|
| Hollywood | 1,074 | 217 days | 69% | $73.1M |
| Granada Hills – Knollwood | 1,062 | 164 days | 60% | $72.7M |
| Arleta – Pacoima | 1,023 | 192 days | 69% | $64.7M |
| Sunland – Tujunga – Lake View Terrace – Shadow Hills | 978 | 198 days | 61% | $61.7M |
| West Los Angeles | 861 | 175 days | 66% | $48.1M |
| Encino – Tarzana | 821 | 176 days | 64% | $52.2M |
| Silver Lake – Echo Park – Elysian Valley | 812 | 182 days | 62% | $51.6M |
| Sherman Oaks – Studio City – Toluca Lake – Cahuenga Pass | 810 | 174 days | 66% | $44.0M |
| Sylmar | 694 | 174 days | 63% | $44.1M |
| Westchester – Playa del Rey | 685 | 188 days | 70% | $47.1M |
| Northridge | 666 | 176 days | 67% | $49.8M |
| Brentwood – Pacific Palisades | 642 | 187 days | 69% | $59.5M |
| Chatsworth – Porter Ranch | 628 | 179 days | 61% | $43.2M |
| Venice | 372 | 290 days | 70% | $23.4M |
| Wilmington – Harbor City | 366 | 259 days | 75% | $27.7M |
| Boyle Heights | 334 | 212 days | 69% | $25.2M |
| Harbor Gateway | 317 | 225 days | 73% | $24.8M |
| San Pedro | 250 | 270 days | 72% | $16.0M |
| Westwood | 219 | 167 days | 65% | $12.3M |
| Bel Air – Beverly Crest | 141 | 277 days | 70% | $13.4M |
| Westlake | 107 | 283 days | 73% | $7.5M |
Check a Los Angeles building permit live
Search any permit number or street address in the City of Los Angeles Open Data registry. Your address stays in this browser tab and is never added to a link or stored.
60-day ADU shot-clock calculator & written notice
California Government Code § 66317 gives local permitting agencies 60 calendar days to ministerially approve or deny a complete Accessory Dwelling Unit application. Enter your application details below to calculate your statutory deadline and assemble a plain written status request for Los Angeles.
- Submittal date
- November 23, 2026
- Day 45 check-in
- January 7, 2027
- Day 60 statutory deadline
- January 22, 2027
- Current status
- 60 days remaining in the 60-day window
Draft written notice to LADBS Plan Check Supervisor (review before sending)
November 23, 2026 To: Plan Check Supervisor Los Angeles Department of Building and Safety (LADBS) 201 N. Figueroa Street, Los Angeles, CA 90012 CC: California Department of Housing and Community Development (HCD) Housing Accountability Unit Subject: Request for Ministerial ADU Review Status & Consolidated Corrections Under CA Gov. Code § 66317 — Permit #[PERMIT APPLICATION NUMBER] Dear Plan Check Supervisor, I am writing regarding Accessory Dwelling Unit (ADU) Permit Application #[PERMIT APPLICATION NUMBER] for [PROPERTY STREET ADDRESS, LOS ANGELES, CA], submitted on November 23, 2026. Under California Government Code § 66317, the 60-day ministerial review window for a complete ADU application runs through January 22, 2027. Pursuant to California Government Code § 66317, I respectfully request: 1. Immediate ministerial approval of this complete ADU application, OR 2. A single, complete, written set of objective code comments citing the exact code section for every remaining item so that all corrections can be resolved without serial plan-check cycles. Please respond in writing with the current plan-check status, assigned plan checker, and next action date. Sincerely, [YOUR FULL NAME] Permit Reference: #[PERMIT APPLICATION NUMBER] Property Address: [PROPERTY STREET ADDRESS, LOS ANGELES, CA]
Election.org publishes official City of Los Angeles permit data and California statutory references for public accountability and citizen self-help. This draft is informational and is not legal representation; review every detail before sending.
Related Los Angeles public records
- Los Angeles elected officialsMayor, City Attorney, Controller, and all 15 City Council districts.
- Los Angeles 2026 general election guideCertified candidates and city ballot measures.
- Los Angeles public commitment trackerDated official records tied to Los Angeles officeholders.
- Local government by addressFind the city, county, school, and special-district offices for an address.
Sources & notes
Permit registryCity of Los Angeles Department of Building and Safety (LADBS) via City of Los Angeles Open Data
Open data endpointdata.lacity.org/resource/pi9x-tg5x.json
StatuteCalifornia Government Code § 66317 (60-day ministerial ADU review)
Data updatedNov 14, 2026