Los Angeles City Council District 3: ADU permit timelines
Across 3,029 issued Accessory Dwelling Unit permits in Council District 3, applications averaged 162 calendar days (28 days shorter than the Los Angeles citywide average of 190 days), with 63% exceeding California’s 60-day review window under Gov. Code § 66317.
- 32,323 total LADBS permits in area
- 3,029 issued ADUs
- 1,894 ADUs over 60 days
- Updated Nov 14, 2026
See Bob Blumenfield’s official record
Computed from City of Los Angeles Department of Building and Safety (LADBS) submittal and issuance dates in Los Angeles Open Data.
From City of Los Angeles Open Data (LADBS), as of November 14, 2026.
- Issued ADUs measured
- 3,029
- Average wait
- 162 days
- Over 60-day statutory window
- 63%
- Declared ADU valuation
- $190.4 million
Elected representative for this district
Los Angeles City Council members oversee citywide housing policy, departmental budgets, and constituent permitting escalations for their district.
Recent ADU permit filings in Council District 3
The 15 most recently submitted Accessory Dwelling Unit filings recorded by LADBS in Council District 3. You can select any filing below to calculate its 60-day statutory deadline and prepare a written status request.
| Permit number | Address | Submitted | Status | Elapsed | Declared value |
|---|---|---|---|---|---|
| 25016-20003-04842SUPPLEMENTAL PERMIT TO 25016 - 20000 - 04842 TO REVISE PLANS AND STRUCTURAL PLANS | 19012-19012 1/2 W KESWICK STZone RA-1 | Nov 12, 2026 | Issued | 0 days | $501 |
| 25010-20001-04838SUPPLEMENTAL PERMIT FOR 25010-20000-04838 TO CORRECT TYPE OF FIRE SPRINKLER SYSTEM TO NFPA-13R IN WORK DESCRIPTION TO MATCH INVENTORY **** NO FEE DEPT ERROR **** | 5329 1/2 N TAMPA AVEZone RA-1 | Nov 10, 2026 | Issued | 0 days | — |
| 19010-20002-01688Supplemental permit to 19010-20000-01688 to revise the height | 7020 N GAZETTE AVEZone RS-1-RIO | Nov 6, 2026 | Permit Finaled | 0 days | $501 |
| 26010-20002-00847SUPPL. PERMIT TO 26010-20000-00847 TO REVISE THE (E) FLOOR PLAN LAYOUT | 20608 W LEMAY STZone RS-1-RIO | Oct 30, 2026 | Permit Finaled | 0 days | $2,501 |
| 25010-20002-00969NO FEE DEPT. ERROR - SUPPLEMENTAL PERMIT TO 25010 - 20000 - 00969 TO CORRECT TOTAL WIDTH IN STRUCTURAL INVENTORY TO BE 24.67', INCLUDE THE FLOOR AREA BELOW LANDINGS WITH POSTS (31 | 7531-7531 1/2 N MILWOOD AVEZone R1-1 | Oct 28, 2026 | Issued | 0 days | — |
| 25010-20001-00104SUPPLEMENTAL TO 25010-20000-00104: TO CORRECT BUILDING WIDTH DIMENSION TO 28' AND ADD PATIO COVER TO USE CODE. *NO FEE DEPARTMENT ERROR | 19920-19920 1/2 W KITTRIDGE STZone R1-1-RIO | Oct 27, 2026 | Issued | 0 days | — |
| 25016-30001-36199Supplemental ref to "Revise scope of work to conversion of attached garage to ADU per GCS 65852.2(e)(1)(A) in (E) 1-story SFD & update use code and structural inventory . All work | 20615-20617 W SCHOENBORN STZone RS-1 | Oct 23, 2026 | Permit Finaled | 0 days | — |
| 22014-20002-01380**NO FEE. DEPARTMENT ERROR.** SUPPLEMENTAL PERMIT TO 22014-20001-01380 TO REVISE SCOPE OF WORK TO - REMOVE PORTION OF GARAGE. TWO STORY ADDITION TO AND CONVERT DETACHED GARAGE TO A | 8359 N DELCO AVEZone RS-1 | Oct 22, 2026 | Permit Finaled | 0 days | — |
| 26014-20001-00923SUPPLEMENTAL PERMIT TO 26014-20000-00923 TO CORRECT BUILDING HEIGHT PER SITE SURVEY. | 5116-5116 1/2 N CHIMINEAS AVEZone R1-1 | Oct 21, 2026 | Issued | 0 days | $501 |
| 22010-30006-05821Supplemental permit to 22010-30000-05821 to update the address.**No fee departement error** | 6116-6118 N MAURY AVEZone RE11-1 | Oct 19, 2026 | Permit Finaled | 0 days | — |
| 25010-20002-00467ePlan: Supplemental to permit #: 25010-20000-00467 to CHANGE fuel type from all-electric to full gas. REVISE TITLE 24 | 7440-7440 1/2 N OWENSMOUTH AVEZone R1-1 | Oct 16, 2026 | Permit Finaled | 13 days | $501 |
| 25010-20002-03034EPLANSupplemental to 25010-10000-03034 For Relocation of the proposed solar panels; From new ADU roof to existing SFD roof. | 22241 W WYANDOTTE STZone RS-1 | Oct 15, 2026 | Issued | 11 days | $501 |
| 26010-10000-05162NEW DETACHED ADU PER GC & 66323(a)(2), ONE-STORY, 24'10'' X 22', TYPE VB CONSTRUCTION, SEE COMMENTS. | 18624 W ROCOSO PLZone RE11-1 | Oct 14, 2026 | CofO Issued | 0 days | $5,000 |
| 24014-20001-04669SUPPLEMENTAL TO 24014-20000-04669: TO CORRECT STRUCTURAL INVENTORY AND WORK DESCRIPTION TO READ: PROPOSE 541SF ADDITION AT FRONT TO (E) 1524SF SFD, ADD 356SF PATIO COVER AT REAR, C | 7809-7813 N MCNULTY AVEZone RS-1 | Oct 9, 2026 | Permit Finaled | 0 days | — |
| 25010-30002-01389Supplemental to 25010-20000-01389to capture height change in the structural inventory. *** Department error NO FEE *** | 7858 N WILBUR AVEZone RA-1 | Oct 2, 2026 | Permit Finaled | 0 days | — |
Check a Los Angeles building permit live
Search any permit number or street address in the City of Los Angeles Open Data registry. Your address stays in this browser tab and is never added to a link or stored.
60-day ADU shot-clock calculator & written notice
California Government Code § 66317 gives local permitting agencies 60 calendar days to ministerially approve or deny a complete Accessory Dwelling Unit application. Enter your application details below to calculate your statutory deadline and assemble a plain written status request for Los Angeles City Council District 3.
- Submittal date
- November 23, 2026
- Day 45 check-in
- January 7, 2027
- Day 60 statutory deadline
- January 22, 2027
- Current status
- 60 days remaining in the 60-day window
Review written notice to LADBS Plan Check Supervisor
November 23, 2026
To: Plan Check Supervisor
Los Angeles Department of Building and Safety (LADBS)
201 N. Figueroa Street, Los Angeles, CA 90012
CC: Office of Los Angeles City Council District 3 (Bob Blumenfield); California Department of Housing and Community Development (HCD) Housing Accountability Unit
Subject: Request for Ministerial ADU Review Status & Consolidated Corrections Under CA Gov. Code § 66317 — Permit #[PERMIT APPLICATION NUMBER]
Dear Plan Check Supervisor,
I am writing regarding Accessory Dwelling Unit (ADU) Permit Application #[PERMIT APPLICATION NUMBER] for [PROPERTY STREET ADDRESS, LOS ANGELES, CA], submitted on November 23, 2026.
Under California Government Code § 66317, the 60-day ministerial review window for a complete ADU application runs through January 22, 2027.
Pursuant to California Government Code § 66317, I respectfully request:
1. Immediate ministerial approval of this complete ADU application, OR
2. A single, complete, written set of objective code comments citing the exact code section for every remaining item so that all corrections can be resolved without serial plan-check cycles.
Please respond in writing with the current plan-check status, assigned plan checker, and next action date.
Sincerely,
[YOUR FULL NAME]
Permit Reference: #[PERMIT APPLICATION NUMBER]
Property Address: [PROPERTY STREET ADDRESS, LOS ANGELES, CA]
Election.org publishes official City of Los Angeles permit data and California statutory references for public accountability and citizen self-help. This draft is informational and is not legal representation; review every detail before sending.
Other Los Angeles Council districts
- Bob Blumenfield — City Council District 3Official officeholder record, term dates, and source roster.
- Los Angeles City Council District 1968 issued ADUs · 262 days average · 70% over 60 days
- Los Angeles City Council District 23,537 issued ADUs · 170 days average · 62% over 60 days
- Los Angeles City Council District 42,778 issued ADUs · 178 days average · 63% over 60 days
- Los Angeles City Council District 52,638 issued ADUs · 189 days average · 68% over 60 days
- Los Angeles City Council District 62,587 issued ADUs · 170 days average · 63% over 60 days
Up: All Los Angeles permit timelines, Los Angeles officials, Local government
Sources & notes
Permit registryCity of Los Angeles Department of Building and Safety (LADBS) via City of Los Angeles Open Data
Open data endpointdata.lacity.org/resource/pi9x-tg5x.json
StatuteCalifornia Government Code § 66317 (60-day ministerial ADU review)
Data updatedNov 14, 2026