Los Angeles City Council District 12: ADU permit timelines
Across 3,071 issued Accessory Dwelling Unit permits in Council District 12, applications averaged 166 calendar days (24 days shorter than the Los Angeles citywide average of 190 days), with 61% exceeding California’s 60-day review window under Gov. Code § 66317.
- 39,758 total LADBS permits in area
- 3,071 issued ADUs
- 1,875 ADUs over 60 days
- Updated Nov 14, 2026
See John Lee’s official record
Computed from City of Los Angeles Department of Building and Safety (LADBS) submittal and issuance dates in Los Angeles Open Data.
From City of Los Angeles Open Data (LADBS), as of November 14, 2026.
- Issued ADUs measured
- 3,071
- Average wait
- 166 days
- Over 60-day statutory window
- 61%
- Declared ADU valuation
- $207.1 million
Elected representative for this district
Los Angeles City Council members oversee citywide housing policy, departmental budgets, and constituent permitting escalations for their district.
Recent ADU permit filings in Council District 12
The 15 most recently submitted Accessory Dwelling Unit filings recorded by LADBS in Council District 12. You can select any filing below to calculate its 60-day statutory deadline and prepare a written status request.
| Permit number | Address | Submitted | Status | Elapsed | Declared value |
|---|---|---|---|---|---|
| 25014-20001-01598SUPPLEMENTAL PERMIT FOR 25014-20000-01598 TO REVISE (1) WINDOW SILL HEIGHT & ADD (1) WINDOW **ePlan** | 12014 N EL ORO WAYZone [T]RS-1 | Nov 12, 2026 | Issued | 1 days | $3,000 |
| 26016-20001-17897SUPPL. PERMIT TO 26016-20000-17897 TO REVISE THE (E) PROPOSED FLOOR PLAN. | 11065 N WHITE OAK AVEZone R1-1XL-RFA | Nov 9, 2026 | Issued | 0 days | $2,501 |
| 25010-20003-03890SUPPLEMENTAL PERMIT TO 25010 - 20000 - 03890 TO CORRECT HEIGHT PER SURVEY AND STRUCTURAL INVENTORY TO 20.77' | 18634 W COMMUNITY STZone RS-1 | Nov 9, 2026 | Permit Finaled | 0 days | — |
| 25010-20001-03964SUPPLEMENTAL PERMIT TO 25010-20000-03964 TO REVISE TITLE 24 FROM ALL ELECTRIC TO GAS FUEL TYPE | 8824-8824 1/2 N VALJEAN AVEZone RS-1 | Nov 5, 2026 | Issued | 0 days | $2,501 |
| 26016-20000-30661Permit previously unpermitted conversion of existing covered patio to an ADU per AB 2533. | 8763 N WOODLEY AVEZone RS-1 | Nov 2, 2026 | Issued | 7 days | $5,000 |
| 25010-10001-05547Supplemental to 25010-20000-05547 to collect the additional school fees | 10923 N BEE CANYON ROADZone (T)RA-1-K | Oct 30, 2026 | Issued | 0 days | — |
| 25010-20002-02736Supplemental to 25010-20000-02736to capture1. ALQ & breezeway/patio in the work description2. Adding ALQ & Breezeway/patio dimensions in the inventory3. To capture the address chan | 11959 N NUGENT DRZone RA-1-H | Oct 28, 2026 | Issued | 0 days | $2,051 |
| 26010-20000-05338NEW DETACHED ACCESSORY DWELLING UNIT PER GCS 66323(A)(2). NFPA 13 D THROUGH OUT | 18018 W OSBORNE STZone RA-1 | Oct 27, 2026 | Issued | 10 days | $60,000 |
| 20016-10002-17609supplemental to 20016-10000-17609 to replace the plot plan. no fee department error | 20119-20121 W LEMARSH STZone RE11-1 | Oct 26, 2026 | Permit Finaled | 0 days | — |
| 20010-30006-02930supplemental permit to 20010-30000-02930 to update height | 7399-7399 1/2 N DARNOCH WAYZone RE11-1-H | Oct 23, 2026 | Permit Finaled | 0 days | $2,501 |
| 26014-20000-04073ADDITION TO AND CONVERT DETACHED STORAGE ROOM TO ACCESSORY DWELLING UNIT PER GCS 66323(A)(2). | 9342 N YOLANDA AVEZone RS-1 | Oct 23, 2026 | Issued | 11 days | $50,000 |
| 25010-20002-01305NO FEE DEPT. ERROR - SUPPLEMENTAL PERMIT TO 25010 - 20000 - 01305 TO CORRECT LENGTH IN STRUCTURAL INVENTORY TO 40.33' AND UPDATE WORK DESCRIPTION TO "NEW 2-STORY ACCESSORY DWELLING | 19611 W DEVONSHIRE STZone RA-1-H | Oct 22, 2026 | Permit Finaled | 0 days | — |
| 25010-20001-00924ATTN: JOSEPH RAFOLS Supplemental to 25010-20000-00924 to revise property setbacks and building height to match the survey, and update Title 24 calculations to reflect a gas stove | 11069 N LINDLEY AVEZone (T)RS-1 | Oct 21, 2026 | Issued | 13 days | $501 |
| 26016-20001-24617Eplan - Supplemental to permit #26016-20000-24617 to revise floor plan, and change owner name | 8726 N AMESTOY AVEZone RA-1 | Oct 21, 2026 | Issued | 2 days | $2,501 |
| 26010-20001-00668*NO FEE. DEPARTMENT ERROR* SUPPLEMENTAL PERMIT TO 26010-20000-00668 TO ADD NFPA 13R FIRE SPRINKLERS THROUGHOUT PER APPROVED PLANS AND REVISE STRUCTURAL INVENTORY | 19220 W PARTHENIA ST #1-4Zone R3-1 | Oct 20, 2026 | Issued | 0 days | — |
Check a Los Angeles building permit live
Search any permit number or street address in the City of Los Angeles Open Data registry. Your address stays in this browser tab and is never added to a link or stored.
60-day ADU shot-clock calculator & written notice
California Government Code § 66317 gives local permitting agencies 60 calendar days to ministerially approve or deny a complete Accessory Dwelling Unit application. Enter your application details below to calculate your statutory deadline and assemble a plain written status request for Los Angeles City Council District 12.
- Submittal date
- November 23, 2026
- Day 45 check-in
- January 7, 2027
- Day 60 statutory deadline
- January 22, 2027
- Current status
- 60 days remaining in the 60-day window
Review written notice to LADBS Plan Check Supervisor
November 23, 2026
To: Plan Check Supervisor
Los Angeles Department of Building and Safety (LADBS)
201 N. Figueroa Street, Los Angeles, CA 90012
CC: Office of Los Angeles City Council District 12 (John Lee); California Department of Housing and Community Development (HCD) Housing Accountability Unit
Subject: Request for Ministerial ADU Review Status & Consolidated Corrections Under CA Gov. Code § 66317 — Permit #[PERMIT APPLICATION NUMBER]
Dear Plan Check Supervisor,
I am writing regarding Accessory Dwelling Unit (ADU) Permit Application #[PERMIT APPLICATION NUMBER] for [PROPERTY STREET ADDRESS, LOS ANGELES, CA], submitted on November 23, 2026.
Under California Government Code § 66317, the 60-day ministerial review window for a complete ADU application runs through January 22, 2027.
Pursuant to California Government Code § 66317, I respectfully request:
1. Immediate ministerial approval of this complete ADU application, OR
2. A single, complete, written set of objective code comments citing the exact code section for every remaining item so that all corrections can be resolved without serial plan-check cycles.
Please respond in writing with the current plan-check status, assigned plan checker, and next action date.
Sincerely,
[YOUR FULL NAME]
Permit Reference: #[PERMIT APPLICATION NUMBER]
Property Address: [PROPERTY STREET ADDRESS, LOS ANGELES, CA]
Election.org publishes official City of Los Angeles permit data and California statutory references for public accountability and citizen self-help. This draft is informational and is not legal representation; review every detail before sending.
Other Los Angeles Council districts
- John Lee — City Council District 12Official officeholder record, term dates, and source roster.
- Los Angeles City Council District 1968 issued ADUs · 262 days average · 70% over 60 days
- Los Angeles City Council District 23,537 issued ADUs · 170 days average · 62% over 60 days
- Los Angeles City Council District 33,029 issued ADUs · 162 days average · 63% over 60 days
- Los Angeles City Council District 42,778 issued ADUs · 178 days average · 63% over 60 days
- Los Angeles City Council District 52,638 issued ADUs · 189 days average · 68% over 60 days
Up: All Los Angeles permit timelines, Los Angeles officials, Local government
Sources & notes
Permit registryCity of Los Angeles Department of Building and Safety (LADBS) via City of Los Angeles Open Data
Open data endpointdata.lacity.org/resource/pi9x-tg5x.json
StatuteCalifornia Government Code § 66317 (60-day ministerial ADU review)
Data updatedNov 14, 2026