Los Angeles City Council District 14: ADU permit timelines
Across 1,489 issued Accessory Dwelling Unit permits in Council District 14, applications averaged 225 calendar days (35 days longer than the Los Angeles citywide average of 190 days), with 72% exceeding California’s 60-day review window under Gov. Code § 66317.
- 22,082 total LADBS permits in area
- 1,489 issued ADUs
- 1,066 ADUs over 60 days
- Updated Nov 14, 2026
See Ysabel J. Jurado’s official record
Computed from City of Los Angeles Department of Building and Safety (LADBS) submittal and issuance dates in Los Angeles Open Data.
From City of Los Angeles Open Data (LADBS), as of November 14, 2026.
- Issued ADUs measured
- 1,489
- Average wait
- 225 days
- Over 60-day statutory window
- 72%
- Declared ADU valuation
- $99.7 million
Elected representative for this district
Los Angeles City Council members oversee citywide housing policy, departmental budgets, and constituent permitting escalations for their district.
Recent ADU permit filings in Council District 14
The 15 most recently submitted Accessory Dwelling Unit filings recorded by LADBS in Council District 14. You can select any filing below to calculate its 60-day statutory deadline and prepare a written status request.
| Permit number | Address | Submitted | Status | Elapsed | Declared value |
|---|---|---|---|---|---|
| 25010-10001-05985Supplemental of 25010-10000-05985 for kitchen layout change, electrical meter location change. | 4220 N STILLWELL AVEZone [Q]R1-1D-HCR | Nov 2, 2026 | Issued | 2 days | $2,501 |
| 25014-10003-05653SUPPLEMENTAL TO PERMIT: 25014-10002-05653 NEW FRAMING DESIGN. WORK PER WFPP. | 1597 W GLEN AYLSA AVEZone R1-1 | Oct 20, 2026 | Issued | 8 days | $5,000 |
| 21010-10001-06445SUPPLEMENTAL PERMIT TO PERMIT #21010-10001-06445 TO REVISE WORK DESCRIPTION AS FOLLOWS: ADU ADDITION TO EXISTING DETACHED GARAGE two story ADU 1,200 SQ.FT LAMC 12.22 A.33(b)(1)RE | 2842 N VAQUERO AVEZone R1-1 | Oct 19, 2026 | Issued | 0 days | $501 |
| 25014-20002-02254SUPPLEMENTAL PERMIT TO REVISE PORTION OF BUILDING TO REMAIN(3 OF 3) | 5069-5069 1/2 N HIGHLAND VIEW AVEZone RD1.5-1 | Sep 30, 2026 | Issued | 6 days | $2,501 |
| 26010-10000-04608EPLA: NEW DETACHED ADU PER GC 66323(a)(2) | 5151 1/2 N MOUNT HELENA AVEZone R1-1 | Sep 8, 2026 | Issued | 58 days | $45,000 |
| 26016-10002-06040Supplemental to 26016-10000-06040 to "Revise site and floor plan and updated title 24" | 7277 N FIGUEROA STZone R1-1 | Sep 2, 2026 | Issued | 15 days | $1,000 |
| 24010-10001-04710EPLAN. SUPPLEMENTAL TO PERMIT NO. 24010-10000-04710: To revise height, revise setbacks, revise floor area, & revise structural framing | 4307 N ALPHA STZone [Q]C2-1VL | Aug 28, 2026 | IssuedExceeds 60-day law | 70 days | $501 |
| 25014-30001-01861Supplemental no fee, department error to PCIS #25014-30000-01861 to correct address to reflect range of 1539-1539 3/4 N Tremont St | 1539-1539 3/4 N TREMONT STZone RD1.5-1 | Aug 28, 2026 | Permit Finaled | 0 days | — |
| 25010-10001-04420SUPPLEMENTAL TO PERMIT # 25010-10000-04420, ADDITION OF 2 SKYLIGHTS, REMOVAL OF FUTURE SOLAR AND REVISED WINDOW/DOOR FLASHING & WATERPROOFING DESIGN. | 5005 N TOWNSEND AVEZone R1-1 | Aug 26, 2026 | Issued | 5 days | $800 |
| 25010-10001-03294Supplemental permit to 25010-10000-03294 to revise structural plans only | 5641 E BERKSHIRE DRZone R1-1-HPOZ | Aug 12, 2026 | Issued | 12 days | $2,501 |
| 25010-10002-03297SUPPLEMENTAL PERMIT TO 25010-10000-03297. TO REVISE THE ADU SETBACKS AND FLOOR PLAN TO INCLUDE FIRE RATED WALLS AND EAVES. | 5613 E STRATFORD ROADZone R1-1-HCR | Aug 11, 2026 | Issued | 6 days | $501 |
| 26016-20000-20996PARTIAL FOUNDATION REPLACEMENT. | 1310 1/2 N AVENUE 56Zone R1-1-HCR | Aug 10, 2026 | Issued | 3 days | $3,000 |
| 25010-10001-03824EPLAN: Supplemental to PCIS #25010-10000-03824 to reduce size of detached 1 story ADU per GCS 66323 (a)(4) | 3410 N CHADWICK DRZone RD3-1 | Jul 29, 2026 | Issued | 13 days | $100 |
| 26014-10000-02898Eeplan:(E) GARAGE CONVERSION AND ADDITION TO (N) 1-STORY DETACHED ADU (35' x 20') PER GC 66323(a)(2) | 1430 N ARMADALE AVEZone R1-1 | Jul 28, 2026 | IssuedExceeds 60-day law | 100 days | $100,000 |
| 25010-10001-03538Supplemental to revise the height of the structure. | 1481 N CAMPUS ROADZone R1-1 | Jul 14, 2026 | Issued | 13 days | $501 |
Check a Los Angeles building permit live
Search any permit number or street address in the City of Los Angeles Open Data registry. Your address stays in this browser tab and is never added to a link or stored.
60-day ADU shot-clock calculator & written notice
California Government Code § 66317 gives local permitting agencies 60 calendar days to ministerially approve or deny a complete Accessory Dwelling Unit application. Enter your application details below to calculate your statutory deadline and assemble a plain written status request for Los Angeles City Council District 14.
- Submittal date
- November 23, 2026
- Day 45 check-in
- January 7, 2027
- Day 60 statutory deadline
- January 22, 2027
- Current status
- 60 days remaining in the 60-day window
Review written notice to LADBS Plan Check Supervisor
November 23, 2026
To: Plan Check Supervisor
Los Angeles Department of Building and Safety (LADBS)
201 N. Figueroa Street, Los Angeles, CA 90012
CC: Office of Los Angeles City Council District 14 (Ysabel J. Jurado); California Department of Housing and Community Development (HCD) Housing Accountability Unit
Subject: Request for Ministerial ADU Review Status & Consolidated Corrections Under CA Gov. Code § 66317 — Permit #[PERMIT APPLICATION NUMBER]
Dear Plan Check Supervisor,
I am writing regarding Accessory Dwelling Unit (ADU) Permit Application #[PERMIT APPLICATION NUMBER] for [PROPERTY STREET ADDRESS, LOS ANGELES, CA], submitted on November 23, 2026.
Under California Government Code § 66317, the 60-day ministerial review window for a complete ADU application runs through January 22, 2027.
Pursuant to California Government Code § 66317, I respectfully request:
1. Immediate ministerial approval of this complete ADU application, OR
2. A single, complete, written set of objective code comments citing the exact code section for every remaining item so that all corrections can be resolved without serial plan-check cycles.
Please respond in writing with the current plan-check status, assigned plan checker, and next action date.
Sincerely,
[YOUR FULL NAME]
Permit Reference: #[PERMIT APPLICATION NUMBER]
Property Address: [PROPERTY STREET ADDRESS, LOS ANGELES, CA]
Election.org publishes official City of Los Angeles permit data and California statutory references for public accountability and citizen self-help. This draft is informational and is not legal representation; review every detail before sending.
Other Los Angeles Council districts
- Ysabel J. Jurado — City Council District 14Official officeholder record, term dates, and source roster.
- Los Angeles City Council District 1968 issued ADUs · 262 days average · 70% over 60 days
- Los Angeles City Council District 23,537 issued ADUs · 170 days average · 62% over 60 days
- Los Angeles City Council District 33,029 issued ADUs · 162 days average · 63% over 60 days
- Los Angeles City Council District 42,778 issued ADUs · 178 days average · 63% over 60 days
- Los Angeles City Council District 52,638 issued ADUs · 189 days average · 68% over 60 days
Up: All Los Angeles permit timelines, Los Angeles officials, Local government
Sources & notes
Permit registryCity of Los Angeles Department of Building and Safety (LADBS) via City of Los Angeles Open Data
Open data endpointdata.lacity.org/resource/pi9x-tg5x.json
StatuteCalifornia Government Code § 66317 (60-day ministerial ADU review)
Data updatedNov 14, 2026