Los Angeles City Council District 15: ADU permit timelines
Across 1,304 issued Accessory Dwelling Unit permits in Council District 15, applications averaged 246 calendar days (56 days longer than the Los Angeles citywide average of 190 days), with 72% exceeding California’s 60-day review window under Gov. Code § 66317.
- 17,154 total LADBS permits in area
- 1,304 issued ADUs
- 938 ADUs over 60 days
- Updated Nov 14, 2026
See Tim McOsker’s official record
Computed from City of Los Angeles Department of Building and Safety (LADBS) submittal and issuance dates in Los Angeles Open Data.
From City of Los Angeles Open Data (LADBS), as of November 14, 2026.
- Issued ADUs measured
- 1,304
- Average wait
- 246 days
- Over 60-day statutory window
- 72%
- Declared ADU valuation
- $93.0 million
Elected representative for this district
Los Angeles City Council members oversee citywide housing policy, departmental budgets, and constituent permitting escalations for their district.
Recent ADU permit filings in Council District 15
The 15 most recently submitted Accessory Dwelling Unit filings recorded by LADBS in Council District 15. You can select any filing below to calculate its 60-day statutory deadline and prepare a written status request.
| Permit number | Address | Submitted | Status | Elapsed | Declared value |
|---|---|---|---|---|---|
| 24014-10002-05058SUPPLEMENTAL PERMIT TO 24014-10000-05058 TO UPDATE STRUCTURAL INVENTORY FROM 1 UNIT ADU TO 2 UNIT ADUS*NO FEE DEPARTMENT ERROR, NO PLOT PLAN REQUIRED | 11812 3/4-11814 3/4 S VERMONT AVEZone R3-1-CPIO | Sep 30, 2026 | Permit Finaled | 0 days | — |
| 23010-10002-00702SUPPLEMENTAL PERMIT TO 23010-10000-00702 TO CHANGE SCOPE OF WORK FROM "CONVERT (E) SINGLE FAMILY DWELLING AND ATTACHED GARAGE TO A DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A | 1143 W 21ST STZone R1-1XL | Sep 24, 2026 | Issued | 0 days | — |
| 26016-10000-26144Eplan: Supplemental to permit#: 24014-10000-04223to revised the height of the Proposed building from 20ft 11 inches to 21ft 3 inches | 1537 N BANNING BLVDZone R1-1XL-O-CUGU | Sep 24, 2026 | Issued | 18 days | $501 |
| 24014-20001-05108SUPPL. PERMIT TO 24014-20000-05108 TO MOVE THE DOOR LOCATION, REVISE THE SIZE OF THE BEDROOM WINDOW, AND ADD CEILING JOIST. | 10406-10406 1/2 S ANZAC AVEZone R1-1 | Sep 15, 2026 | Issued | 0 days | $2,501 |
| 22010-10002-02704ePlan***Supplemental to permit #22010-10000-02704 - Revision to structural framing plan. | 1309 W EMDEN STZone R1-1XL-O-CUGU | Sep 15, 2026 | Issued | 24 days | $2,501 |
| 22010-10001-01262[PUBICLY HABITABLE SPACE] SUPPLEMENTAL TO 22010-10000-01262 TO CHANGE SCOPE TO (N) 2-CAR GARAGE W/ ATTACHED ACCESSORY DWELLING UNIT PER LAMC 12.33 A.33(B)(1)FIRE SPRINKLER THRU-OUT | 1669-1669 1/2 N WILMINGTON BLVDZone [Q]RD1.5-1XL-O-CUGU | Sep 9, 2026 | Issued | 0 days | $10,000 |
| 22010-10001-05663SUPPLEMENTAL TO 22010-10000-05663 TO CAPTURE MEP FEES | 1702 W 239TH STZone R1-1XL | Sep 1, 2026 | Issued | 0 days | $501 |
| 26010-20000-04400NEW DETACHED ACCESSORY DWELLING UNIT PER GCS 66323(a)(2). | 945 E 112TH STZone R2-1 | Aug 25, 2026 | Issued | 41 days | $80,000 |
| 25010-10001-01248SUPPLEMENTAL TO 25010-10000-01248 TO REVISE TITLE 24 FROM ALL-ELECTRIC TO NATURAL GAS. | 1141 N BANNING BLVDZone R1-1XL-O-CUGU | Aug 25, 2026 | Issued | 7 days | $2,501 |
| 24010-10002-05041ePlan: SUPPLEMENTAL PERMIT TO 24010-10000-05041 TO REVISE TITLE 24 ANALYSIS TO NATURAL GAS. | 759 W 6TH STZone RD1.5-1XL | Aug 24, 2026 | Issued | 10 days | $2,500 |
| 26014-10001-00676ePlan: Supplemental #26014-10000-00676 to revise plans and clarify Addtion From 100 S.F. to 116 S.F on 1st Floor. | 1323-1323 1/2 W SILVIUS AVEZone R1-1XL | Aug 21, 2026 | IssuedExceeds 60-day law | 72 days | $6,060 |
| 25010-10001-01648eplan. Supplemental permit to 25010-10000-01648 to update height of building | 1367 W 1ST STZone R1-1XL | Aug 15, 2026 | Issued | 9 days | — |
| 26014-20001-00502Supplemental permit to 26014-20000-00502 to revised ceiling and enlarg the entry door. | 811 W 133RD STZone R1-1-O | Aug 14, 2026 | Issued | 0 days | $3,000 |
| 23016-10001-35619SUPPLEMENTAL TO CHANGE T24 FROM GAS TO ELECTRIC AT ADU | 809 E IMPERIAL HWYZone RD2-1-CPIO | Aug 11, 2026 | Issued | 13 days | $1,000 |
| 23010-10001-03939SUPPLEMENTAL PERMIT TO 23010-10000-03939: CHANGE T-24 FROM ELECTRIC TO GAS | 805-805 1/2 W IMPERIAL HWYZone RD2-1-CPIO | Aug 6, 2026 | Permit Finaled | 5 days | $501 |
Check a Los Angeles building permit live
Search any permit number or street address in the City of Los Angeles Open Data registry. Your address stays in this browser tab and is never added to a link or stored.
60-day ADU shot-clock calculator & written notice
California Government Code § 66317 gives local permitting agencies 60 calendar days to ministerially approve or deny a complete Accessory Dwelling Unit application. Enter your application details below to calculate your statutory deadline and assemble a plain written status request for Los Angeles City Council District 15.
- Submittal date
- November 23, 2026
- Day 45 check-in
- January 7, 2027
- Day 60 statutory deadline
- January 22, 2027
- Current status
- 60 days remaining in the 60-day window
Review written notice to LADBS Plan Check Supervisor
November 23, 2026
To: Plan Check Supervisor
Los Angeles Department of Building and Safety (LADBS)
201 N. Figueroa Street, Los Angeles, CA 90012
CC: Office of Los Angeles City Council District 15 (Tim McOsker); California Department of Housing and Community Development (HCD) Housing Accountability Unit
Subject: Request for Ministerial ADU Review Status & Consolidated Corrections Under CA Gov. Code § 66317 — Permit #[PERMIT APPLICATION NUMBER]
Dear Plan Check Supervisor,
I am writing regarding Accessory Dwelling Unit (ADU) Permit Application #[PERMIT APPLICATION NUMBER] for [PROPERTY STREET ADDRESS, LOS ANGELES, CA], submitted on November 23, 2026.
Under California Government Code § 66317, the 60-day ministerial review window for a complete ADU application runs through January 22, 2027.
Pursuant to California Government Code § 66317, I respectfully request:
1. Immediate ministerial approval of this complete ADU application, OR
2. A single, complete, written set of objective code comments citing the exact code section for every remaining item so that all corrections can be resolved without serial plan-check cycles.
Please respond in writing with the current plan-check status, assigned plan checker, and next action date.
Sincerely,
[YOUR FULL NAME]
Permit Reference: #[PERMIT APPLICATION NUMBER]
Property Address: [PROPERTY STREET ADDRESS, LOS ANGELES, CA]
Election.org publishes official City of Los Angeles permit data and California statutory references for public accountability and citizen self-help. This draft is informational and is not legal representation; review every detail before sending.
Other Los Angeles Council districts
- Tim McOsker — City Council District 15Official officeholder record, term dates, and source roster.
- Los Angeles City Council District 1968 issued ADUs · 262 days average · 70% over 60 days
- Los Angeles City Council District 23,537 issued ADUs · 170 days average · 62% over 60 days
- Los Angeles City Council District 33,029 issued ADUs · 162 days average · 63% over 60 days
- Los Angeles City Council District 42,778 issued ADUs · 178 days average · 63% over 60 days
- Los Angeles City Council District 52,638 issued ADUs · 189 days average · 68% over 60 days
Up: All Los Angeles permit timelines, Los Angeles officials, Local government
Sources & notes
Permit registryCity of Los Angeles Department of Building and Safety (LADBS) via City of Los Angeles Open Data
Open data endpointdata.lacity.org/resource/pi9x-tg5x.json
StatuteCalifornia Government Code § 66317 (60-day ministerial ADU review)
Data updatedNov 14, 2026