Los Angeles City Council District 7: ADU permit timelines
Across 2,828 issued Accessory Dwelling Unit permits in Council District 7, applications averaged 189 calendar days (1 days shorter than the Los Angeles citywide average of 190 days), with 65% exceeding California’s 60-day review window under Gov. Code § 66317.
- 19,984 total LADBS permits in area
- 2,828 issued ADUs
- 1,835 ADUs over 60 days
- Updated Nov 14, 2026
See Monica Rodriguez’s official record
Computed from City of Los Angeles Department of Building and Safety (LADBS) submittal and issuance dates in Los Angeles Open Data.
From City of Los Angeles Open Data (LADBS), as of November 14, 2026.
- Issued ADUs measured
- 2,828
- Average wait
- 189 days
- Over 60-day statutory window
- 65%
- Declared ADU valuation
- $184.7 million
Elected representative for this district
Los Angeles City Council members oversee citywide housing policy, departmental budgets, and constituent permitting escalations for their district.
Recent ADU permit filings in Council District 7
The 15 most recently submitted Accessory Dwelling Unit filings recorded by LADBS in Council District 7. You can select any filing below to calculate its 60-day statutory deadline and prepare a written status request.
| Permit number | Address | Submitted | Status | Elapsed | Declared value |
|---|---|---|---|---|---|
| 20014-20003-01667SUPPL. PERMIT TO 20014-10000-01667 TO REVISE TITLE 24 | 13416 W HERRON STZone R1-1 | Nov 13, 2026 | Issued | 0 days | $2,501 |
| 25010-20001-04976**NO FEE, DEPARTMENT ERROR** Supplemental permit to 25010-20000-04976 to update structural inventory | 13064 1/2 W GARBER STZone R1-1-O-CUGU | Nov 6, 2026 | Issued | 0 days | — |
| 26014-20001-03300SUPPL. PERMIT TO 26014-20000-03300 TO REVISE THE SITE PLAN | 6431 W CREEMORE LANEZone R1-1-RFA | Nov 4, 2026 | Issued | 6 days | $2,501 |
| 24016-20003-40197SUPPLEMENTAL PERMIT TO 24016-20000-40197 TO UPDATE STRUCTURAL INVENTORY*NO FEE DEPT ERROR* | 12600-12602 N AMBOY AVEZone RS-1 | Nov 4, 2026 | Permit Finaled | 0 days | — |
| 26010-20002-00252SUPP TO PERMIT 26010-20000-00252 TO COLLECT THE GREEN FEES | 9735 N SALOMA AVEZone RS-1 | Nov 3, 2026 | Issued | 0 days | $8,500 |
| 25014-20002-05257SUPPLEMENETAL PERMIT TO 25014-20000-05257 TO CHANGE THE WORK DESCRIPTION TO "CONVERT EX DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER GC 66323(a)(1) WITH ADDITION. T/O & REROOF | 10402 N JARDINE AVEZone R1-1-RFA | Oct 26, 2026 | Issued | 0 days | $2,500 |
| 26010-20003-01560Supplemental to 26010-20000-01560 to capture revision to Structural plan and its Details**1 of 2** | 10747 N REDMONT AVEZone R1-1 | Oct 20, 2026 | Issued | 7 days | $501 |
| 26010-20001-02089SUPPLEMENTAL TO 26010-20000-02089 TO REMOVE THE ALL ELECTRIC REQUIREMENT AND REVISE TITLE 24 | 10959 N SHARP AVEZone RS-1 | Oct 16, 2026 | Issued | 0 days | $2,501 |
| 22010-20002-04150SUPPLEMENTAL TO 22010-20000-04150 FOR REVISION TO AMEND PREVIOUSLY APPROVED PLANS: ADJUST OVERALL BUILDING HEIGHT TO ACCURATELY REFLECT AS-BUILT FIELD CONDITIONS. (22010 - 20001 - | 6327 W HARMAN DRZone RS-1 | Oct 15, 2026 | Permit Finaled | 21 days | $2,501 |
| 24016-20002-40197EPLAN: Supplemental permit to 24016-20000-40197 to update work descirption to CONVERT EXISTING ATTACHED GARAGE TO ADU PER GCS 66323(a)(1)) PER WFPP.*NO FEE DEPT ERROR* | 12600-12602 N AMBOY AVEZone RS-1 | Oct 13, 2026 | Permit Finaled | 0 days | — |
| 26010-20001-00473SUPPLEMENTAL PERMIT FOR 26010-20000-00473 TO REVISE SITE PLAN & RELOCATE ACCESSORY DWELLING UNIT ** ePlan ** | 11327 1/2 W SUNBURST STZone RS-1 | Oct 13, 2026 | Issued | 9 days | $2,500 |
| 22014-20002-03516SUPPLEMENTAL PERMIT TO 22014-20000-03516 TO REVISE THE FLOOR AND STRUCTURAL PLANS. REMOVE (E) ATTACHED PATIO COVER. | 14259 W HUBBARD STZone R1-1 | Oct 1, 2026 | Issued | 4 days | $2,501 |
| 26016-20000-26953CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 66323(a)(1). | 9936 N LAUREL CANYON BLVDZone R1-1 | Oct 1, 2026 | Issued | 27 days | $75,000 |
| 26014-10000-03756REAR ADDITION AND REMODEL OF SFD WITH ATTACHED GARAGED FOR NEW MASTER BEDROOM AND ATTACHED ADU PER ORDINANCE | 14322-14324 W BEAVER STZone R1-1 | Sep 30, 2026 | Issued | 35 days | $93,000 |
| 26010-20002-02443SUPPLEMENTAL TO PERMIT# 26010-20000-02443 TO INCLUDE METHANE DESIGN PLANS AND REPORT IN LIEU OF LEVEL 5 AND REVISE FOUNDATION PLAN ACCORDINGLY. | 13774-13774 1/2 W JUDD STZone R1-1-O-CUGU | Sep 29, 2026 | Issued | 0 days | $2,500 |
Check a Los Angeles building permit live
Search any permit number or street address in the City of Los Angeles Open Data registry. Your address stays in this browser tab and is never added to a link or stored.
60-day ADU shot-clock calculator & written notice
California Government Code § 66317 gives local permitting agencies 60 calendar days to ministerially approve or deny a complete Accessory Dwelling Unit application. Enter your application details below to calculate your statutory deadline and assemble a plain written status request for Los Angeles City Council District 7.
- Submittal date
- November 23, 2026
- Day 45 check-in
- January 7, 2027
- Day 60 statutory deadline
- January 22, 2027
- Current status
- 60 days remaining in the 60-day window
Review written notice to LADBS Plan Check Supervisor
November 23, 2026
To: Plan Check Supervisor
Los Angeles Department of Building and Safety (LADBS)
201 N. Figueroa Street, Los Angeles, CA 90012
CC: Office of Los Angeles City Council District 7 (Monica Rodriguez); California Department of Housing and Community Development (HCD) Housing Accountability Unit
Subject: Request for Ministerial ADU Review Status & Consolidated Corrections Under CA Gov. Code § 66317 — Permit #[PERMIT APPLICATION NUMBER]
Dear Plan Check Supervisor,
I am writing regarding Accessory Dwelling Unit (ADU) Permit Application #[PERMIT APPLICATION NUMBER] for [PROPERTY STREET ADDRESS, LOS ANGELES, CA], submitted on November 23, 2026.
Under California Government Code § 66317, the 60-day ministerial review window for a complete ADU application runs through January 22, 2027.
Pursuant to California Government Code § 66317, I respectfully request:
1. Immediate ministerial approval of this complete ADU application, OR
2. A single, complete, written set of objective code comments citing the exact code section for every remaining item so that all corrections can be resolved without serial plan-check cycles.
Please respond in writing with the current plan-check status, assigned plan checker, and next action date.
Sincerely,
[YOUR FULL NAME]
Permit Reference: #[PERMIT APPLICATION NUMBER]
Property Address: [PROPERTY STREET ADDRESS, LOS ANGELES, CA]
Election.org publishes official City of Los Angeles permit data and California statutory references for public accountability and citizen self-help. This draft is informational and is not legal representation; review every detail before sending.
Other Los Angeles Council districts
- Monica Rodriguez — City Council District 7Official officeholder record, term dates, and source roster.
- Los Angeles City Council District 1968 issued ADUs · 262 days average · 70% over 60 days
- Los Angeles City Council District 23,537 issued ADUs · 170 days average · 62% over 60 days
- Los Angeles City Council District 33,029 issued ADUs · 162 days average · 63% over 60 days
- Los Angeles City Council District 42,778 issued ADUs · 178 days average · 63% over 60 days
- Los Angeles City Council District 52,638 issued ADUs · 189 days average · 68% over 60 days
Up: All Los Angeles permit timelines, Los Angeles officials, Local government
Sources & notes
Permit registryCity of Los Angeles Department of Building and Safety (LADBS) via City of Los Angeles Open Data
Open data endpointdata.lacity.org/resource/pi9x-tg5x.json
StatuteCalifornia Government Code § 66317 (60-day ministerial ADU review)
Data updatedNov 14, 2026