Northeast Los Angeles, Los Angeles: ADU permit timelines
Across 2,334 issued Accessory Dwelling Unit permits in Northeast Los Angeles, applications averaged 229 calendar days (39 days longer than the Los Angeles citywide average of 190 days), with 69% exceeding California’s 60-day review window under Gov. Code § 66317.
- 26,189 total LADBS permits in area
- 2,334 issued ADUs
- 1,603 ADUs over 60 days
- Updated Nov 14, 2026
Compare all 15 Los Angeles Council districts
Computed from City of Los Angeles Department of Building and Safety (LADBS) submittal and issuance dates in Los Angeles Open Data.
From City of Los Angeles Open Data (LADBS), as of November 14, 2026.
- Issued ADUs measured
- 2,334
- Average wait
- 229 days
- Over 60-day statutory window
- 69%
- Declared ADU valuation
- $146.7 million
Recent ADU permit filings in Northeast Los Angeles
The 15 most recently submitted Accessory Dwelling Unit filings recorded by LADBS in Northeast Los Angeles. You can select any filing below to calculate its 60-day statutory deadline and prepare a written status request.
| Permit number | Address | Submitted | Status | Elapsed | Declared value |
|---|---|---|---|---|---|
| 26014-20001-02386SUPPLEMENTAL PERMIT TO 26014-20000-02386 TO REMOVE THE (E) WOOD POSTS ON 1ST FLOOR AND REPLACE WINDOW AND SWING DOOR LEADING TO A NEW BEDROOM WITH FRENCH DOORS, NO WORK PROPOSED O | 4076-4076 1/2 N VESELICH AVEZone R1-1-RIO | Nov 10, 2026 | Issued | 0 days | $2,501 |
| 25010-10001-05985Supplemental of 25010-10000-05985 for kitchen layout change, electrical meter location change. | 4220 N STILLWELL AVEZone [Q]R1-1D-HCR | Nov 2, 2026 | Issued | 2 days | $2,501 |
| 25014-10003-05653SUPPLEMENTAL TO PERMIT: 25014-10002-05653 NEW FRAMING DESIGN. WORK PER WFPP. | 1597 W GLEN AYLSA AVEZone R1-1 | Oct 20, 2026 | Issued | 8 days | $5,000 |
| 21010-10001-06445SUPPLEMENTAL PERMIT TO PERMIT #21010-10001-06445 TO REVISE WORK DESCRIPTION AS FOLLOWS: ADU ADDITION TO EXISTING DETACHED GARAGE two story ADU 1,200 SQ.FT LAMC 12.22 A.33(b)(1)RE | 2842 N VAQUERO AVEZone R1-1 | Oct 19, 2026 | Issued | 0 days | $501 |
| 26016-10002-15722EPLAN. SUPPLEMENTAL TO 26016-10000-15722 TO ADD 2 NEW SKYLIGHTS | 4044 N SOMERS AVEZone R1-1-CDO | Oct 9, 2026 | Issued | 11 days | $2,000 |
| 25014-10002-01085**NO FEE, DEPARTMENT ERROR** Supplemental permit to 25014-10000-01085 to update structural inventory | 3842 1/2 W AVENUE 41Zone RD2-1-CDO | Oct 9, 2026 | Issued | 0 days | — |
| 23010-30001-00324***No Fee Department Error***Supplemental permit to permit #23010-10000-00324 to remove fire sprinklers from structural inventory. | 3366 E HOLYOKE DRZone R1-1 | Oct 7, 2026 | Issued | 0 days | — |
| 26016-10000-27498EPLAN. CONVERT (E) GARAGE AND NEW ADDITION TO (N) DETACHED ADU | 3511 1/2 W LARGA AVEZone R1-1-RIO | Oct 6, 2026 | Issued | 20 days | $50,000 |
| 25014-20002-02254SUPPLEMENTAL PERMIT TO REVISE PORTION OF BUILDING TO REMAIN(3 OF 3) | 5069-5069 1/2 N HIGHLAND VIEW AVEZone RD1.5-1 | Sep 30, 2026 | Issued | 6 days | $2,501 |
| 23016-20002-01906SUPPL. PERMIT TO 23016-20000-01906 TO REVISE THE CEILING JOIST SIZE AND FOOTING ALONG EAST. | 4128 1/2 N GRIFFIN AVEZone [Q]RD3-1D-HPOZ | Sep 21, 2026 | Issued | 0 days | $2,501 |
| 26010-10000-04608EPLA: NEW DETACHED ADU PER GC 66323(a)(2) | 5151 1/2 N MOUNT HELENA AVEZone R1-1 | Sep 8, 2026 | Issued | 58 days | $45,000 |
| 26016-10002-06040Supplemental to 26016-10000-06040 to "Revise site and floor plan and updated title 24" | 7277 N FIGUEROA STZone R1-1 | Sep 2, 2026 | Issued | 15 days | $1,000 |
| 24010-10001-04710EPLAN. SUPPLEMENTAL TO PERMIT NO. 24010-10000-04710: To revise height, revise setbacks, revise floor area, & revise structural framing | 4307 N ALPHA STZone [Q]C2-1VL | Aug 28, 2026 | IssuedExceeds 60-day law | 70 days | $501 |
| 25014-10001-01085eplan. Supplemental permit to 25014-10000-01085 to revise doors and windows. | 3842 1/2 W AVENUE 41Zone RD2-1-CDO | Aug 28, 2026 | Issued | 6 days | — |
| 25014-30001-01861Supplemental no fee, department error to PCIS #25014-30000-01861 to correct address to reflect range of 1539-1539 3/4 N Tremont St | 1539-1539 3/4 N TREMONT STZone RD1.5-1 | Aug 28, 2026 | Permit Finaled | 0 days | — |
Check a Los Angeles building permit live
Search any permit number or street address in the City of Los Angeles Open Data registry. Your address stays in this browser tab and is never added to a link or stored.
60-day ADU shot-clock calculator & written notice
California Government Code § 66317 gives local permitting agencies 60 calendar days to ministerially approve or deny a complete Accessory Dwelling Unit application. Enter your application details below to calculate your statutory deadline and assemble a plain written status request for Northeast Los Angeles, Los Angeles.
- Submittal date
- November 23, 2026
- Day 45 check-in
- January 7, 2027
- Day 60 statutory deadline
- January 22, 2027
- Current status
- 60 days remaining in the 60-day window
Review written notice to LADBS Plan Check Supervisor
November 23, 2026
To: Plan Check Supervisor
Los Angeles Department of Building and Safety (LADBS)
201 N. Figueroa Street, Los Angeles, CA 90012
CC: California Department of Housing and Community Development (HCD) Housing Accountability Unit
Subject: Request for Ministerial ADU Review Status & Consolidated Corrections Under CA Gov. Code § 66317 — Permit #[PERMIT APPLICATION NUMBER]
Dear Plan Check Supervisor,
I am writing regarding Accessory Dwelling Unit (ADU) Permit Application #[PERMIT APPLICATION NUMBER] for [PROPERTY STREET ADDRESS, LOS ANGELES, CA], submitted on November 23, 2026.
Under California Government Code § 66317, the 60-day ministerial review window for a complete ADU application runs through January 22, 2027.
Pursuant to California Government Code § 66317, I respectfully request:
1. Immediate ministerial approval of this complete ADU application, OR
2. A single, complete, written set of objective code comments citing the exact code section for every remaining item so that all corrections can be resolved without serial plan-check cycles.
Please respond in writing with the current plan-check status, assigned plan checker, and next action date.
Sincerely,
[YOUR FULL NAME]
Permit Reference: #[PERMIT APPLICATION NUMBER]
Property Address: [PROPERTY STREET ADDRESS, LOS ANGELES, CA]
Election.org publishes official City of Los Angeles permit data and California statutory references for public accountability and citizen self-help. This draft is informational and is not legal representation; review every detail before sending.
Other Los Angeles Community Plan Areas
- West Adams – Baldwin Hills – Leimert, Los Angeles2,613 issued ADUs · 204 days average · 67% over 60 days
- South Los Angeles, Los Angeles2,603 issued ADUs · 217 days average · 72% over 60 days
- Wilshire, Los Angeles2,286 issued ADUs · 197 days average · 68% over 60 days
- Reseda – West Van Nuys, Los Angeles2,025 issued ADUs · 155 days average · 63% over 60 days
- Canoga Park – West Hills – Winnetka – Woodland Hills, Los Angeles2,021 issued ADUs · 155 days average · 60% over 60 days
- North Hollywood – Valley Village, Los Angeles1,890 issued ADUs · 171 days average · 61% over 60 days
Up: All Los Angeles permit timelines, Los Angeles officials, Local government
Sources & notes
Permit registryCity of Los Angeles Department of Building and Safety (LADBS) via City of Los Angeles Open Data
Open data endpointdata.lacity.org/resource/pi9x-tg5x.json
StatuteCalifornia Government Code § 66317 (60-day ministerial ADU review)
Data updatedNov 14, 2026