West Adams – Baldwin Hills – Leimert, Los Angeles: ADU permit timelines
Across 2,613 issued Accessory Dwelling Unit permits in West Adams – Baldwin Hills – Leimert, applications averaged 204 calendar days (14 days longer than the Los Angeles citywide average of 190 days), with 67% exceeding California’s 60-day review window under Gov. Code § 66317.
- 21,108 total LADBS permits in area
- 2,613 issued ADUs
- 1,754 ADUs over 60 days
- Updated Nov 14, 2026
Compare all 15 Los Angeles Council districts
Computed from City of Los Angeles Department of Building and Safety (LADBS) submittal and issuance dates in Los Angeles Open Data.
From City of Los Angeles Open Data (LADBS), as of November 14, 2026.
- Issued ADUs measured
- 2,613
- Average wait
- 204 days
- Over 60-day statutory window
- 67%
- Declared ADU valuation
- $159.5 million
Recent ADU permit filings in West Adams – Baldwin Hills – Leimert
The 15 most recently submitted Accessory Dwelling Unit filings recorded by LADBS in West Adams – Baldwin Hills – Leimert. You can select any filing below to calculate its 60-day statutory deadline and prepare a written status request.
| Permit number | Address | Submitted | Status | Elapsed | Declared value |
|---|---|---|---|---|---|
| 22016-10001-06538NO FEE DEPT. ERROR.SUPPLEMENTAL TO 22016-10000-06538 TO CAPTURE USE CODE, CORRECT THE LEGAL DESCRIPTION, AND CAPTURE 2 ADU'S IN INVENTORY. | 3417 1/2 S 12TH AVEZone RD1.5-1 | Nov 6, 2026 | Permit Finaled | 0 days | — |
| 25010-10001-03419ePlanATTN: Zena Haddis/Chiharu Suzuki Emailed on 11/02/2026SUPPLEMENTAL PLAN CHECK REVISION TO APPROVED PLANS (APPROVED 05/18/2026) UNDER APPLICATION NOS. 25010-10000-03419, 25014- | 4227 S LEIMERT BLVDZone R3-1 | Nov 5, 2026 | Issued | 7 days | $2,501 |
| 19016-10002-01006SUPPLEMENTAL PERMIT TO 19016-10000-01006 TO REVISE SCOPE OF WORK TO: NEW ADDITION AND CONVERSION OF (E) 2-STORY GARAGE/REC ROOM TO TWO ADUS PER GCS 65852.2(e)(1)(d) AND LAMC 12.22 | 1725 1/2-1727 1/2 S ORANGE DRZone RD2-1-O | Oct 28, 2026 | Permit Finaled | 0 days | — |
| 26016-30003-17543supplemental to permit to 26016-30000-177543 to update the structural inventroy .***No fee department Error*** | 5225-5225 3/4 W 20TH STZone RD1.5-1 | Oct 26, 2026 | Permit Finaled | 0 days | — |
| 23014-30003-04951supplemental to 23014-30000-04951 to remove sprinkler from inventory. no fee department error. | 5171 W OBAMA BLVDZone R1-1 | Oct 23, 2026 | Issued | 0 days | — |
| 26010-10000-04997EPLAN-NEW DETACHED ACCESSORY DWELLING UNIT PER GCS 66323(a)(2) | 4719 S VAN NESS AVEZone R2-1 | Oct 15, 2026 | Issued | 23 days | $70,000 |
| 26014-10001-01322ePlan. Supplemental to 26014-10000-01322 to remove two windows and revise cathedral ceiling. no other changes | 3826 S DEGNAN BLVDZone R1-1 | Oct 13, 2026 | Issued | 3 days | $1,000 |
| 26010-20000-05105NEW DETACHED ACCESSORY DWELLING UNIT PER GCS 66323(A)(2)COMPLY WITH DEPARTMENT ORDER effective date 07/03/2026. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE. CEIS Case Number is 1 | 5579 W HOMESIDE AVEZone RD1.5-1 | Oct 9, 2026 | Issued | 24 days | $140,000 |
| 26014-10001-02000eplan. SUPPLEMENTAL PERMIT TO 26014-10000-02000 TO RELOCATE THE ENTRY DOORS FOR BOTH UNITS AND REVISE 1ST FLOOR LAYOUT. | 2812 S ALSACE AVEZone RD1.5-1 | Oct 7, 2026 | Issued | 28 days | — |
| 26010-10002-01507Supplemental to Permit No. 26010-10000-01507 to revise the separation between the proposed ADU and existing garage | 2764 W 38TH PLZone R1-1 | Oct 7, 2026 | Issued | 2 days | $1,000 |
| 25010-10002-02082SUPPLEMENTAL TO PCIS# 25010-10000-02082 TO UPDATE TITLE T24 AND REVISE SITE PLAN FOR LOCATION OF WATER HEATER. CONVERT STOVE/RANGE AND DRYER FROM ELECTRIC TO GAS. NO CHANGE ON BUIL | 3022 S HILLCREST DRZone R1-1 | Oct 6, 2026 | Issued | 2 days | $1,000 |
| 25014-10002-04626Supplemental to 25014-10000-04626 to add two additional skylights. One in the bedroom and one in the living/kitchen area | 5740 S WEST BLVDZone R1-1 | Oct 2, 2026 | Issued | 5 days | $4,000 |
| 25010-10002-05849SUPPLEMENTAL PERMIT TO 25010-10000-05849 TO REVISE TITLE-24 | 6027 S 10TH AVEZone R3-1 | Oct 1, 2026 | Issued | 19 days | $2,500 |
| 26010-20002-00117SUPPLEMENTAL PERMIT TO 26010-10000-00117 TO REVISE TITLE-24 | 6033-6033 1/2 S 10TH AVEZone R3-1 | Oct 1, 2026 | Issued | 19 days | $501 |
| 26010-20002-00115SUPPLEMENTAL PERMIT TO 26010-10000-00115 TO REVISE TITLE-24 | 6031-6031 1/2 S 10TH AVEZone R3-1 | Oct 1, 2026 | Issued | 19 days | $501 |
Check a Los Angeles building permit live
Search any permit number or street address in the City of Los Angeles Open Data registry. Your address stays in this browser tab and is never added to a link or stored.
60-day ADU shot-clock calculator & written notice
California Government Code § 66317 gives local permitting agencies 60 calendar days to ministerially approve or deny a complete Accessory Dwelling Unit application. Enter your application details below to calculate your statutory deadline and assemble a plain written status request for West Adams – Baldwin Hills – Leimert, Los Angeles.
- Submittal date
- November 23, 2026
- Day 45 check-in
- January 7, 2027
- Day 60 statutory deadline
- January 22, 2027
- Current status
- 60 days remaining in the 60-day window
Review written notice to LADBS Plan Check Supervisor
November 23, 2026
To: Plan Check Supervisor
Los Angeles Department of Building and Safety (LADBS)
201 N. Figueroa Street, Los Angeles, CA 90012
CC: California Department of Housing and Community Development (HCD) Housing Accountability Unit
Subject: Request for Ministerial ADU Review Status & Consolidated Corrections Under CA Gov. Code § 66317 — Permit #[PERMIT APPLICATION NUMBER]
Dear Plan Check Supervisor,
I am writing regarding Accessory Dwelling Unit (ADU) Permit Application #[PERMIT APPLICATION NUMBER] for [PROPERTY STREET ADDRESS, LOS ANGELES, CA], submitted on November 23, 2026.
Under California Government Code § 66317, the 60-day ministerial review window for a complete ADU application runs through January 22, 2027.
Pursuant to California Government Code § 66317, I respectfully request:
1. Immediate ministerial approval of this complete ADU application, OR
2. A single, complete, written set of objective code comments citing the exact code section for every remaining item so that all corrections can be resolved without serial plan-check cycles.
Please respond in writing with the current plan-check status, assigned plan checker, and next action date.
Sincerely,
[YOUR FULL NAME]
Permit Reference: #[PERMIT APPLICATION NUMBER]
Property Address: [PROPERTY STREET ADDRESS, LOS ANGELES, CA]
Election.org publishes official City of Los Angeles permit data and California statutory references for public accountability and citizen self-help. This draft is informational and is not legal representation; review every detail before sending.
Other Los Angeles Community Plan Areas
- South Los Angeles, Los Angeles2,603 issued ADUs · 217 days average · 72% over 60 days
- Northeast Los Angeles, Los Angeles2,334 issued ADUs · 229 days average · 69% over 60 days
- Wilshire, Los Angeles2,286 issued ADUs · 197 days average · 68% over 60 days
- Reseda – West Van Nuys, Los Angeles2,025 issued ADUs · 155 days average · 63% over 60 days
- Canoga Park – West Hills – Winnetka – Woodland Hills, Los Angeles2,021 issued ADUs · 155 days average · 60% over 60 days
- North Hollywood – Valley Village, Los Angeles1,890 issued ADUs · 171 days average · 61% over 60 days
Up: All Los Angeles permit timelines, Los Angeles officials, Local government
Sources & notes
Permit registryCity of Los Angeles Department of Building and Safety (LADBS) via City of Los Angeles Open Data
Open data endpointdata.lacity.org/resource/pi9x-tg5x.json
StatuteCalifornia Government Code § 66317 (60-day ministerial ADU review)
Data updatedNov 14, 2026