Palms – Mar Vista – Del Rey, Los Angeles: ADU permit timelines
Across 1,146 issued Accessory Dwelling Unit permits in Palms – Mar Vista – Del Rey, applications averaged 177 calendar days (13 days shorter than the Los Angeles citywide average of 190 days), with 70% exceeding California’s 60-day review window under Gov. Code § 66317.
- 14,329 total LADBS permits in area
- 1,146 issued ADUs
- 805 ADUs over 60 days
- Updated Nov 14, 2026
Compare all 15 Los Angeles Council districts
Computed from City of Los Angeles Department of Building and Safety (LADBS) submittal and issuance dates in Los Angeles Open Data.
From City of Los Angeles Open Data (LADBS), as of November 14, 2026.
- Issued ADUs measured
- 1,146
- Average wait
- 177 days
- Over 60-day statutory window
- 70%
- Declared ADU valuation
- $70.8 million
Recent ADU permit filings in Palms – Mar Vista – Del Rey
The 15 most recently submitted Accessory Dwelling Unit filings recorded by LADBS in Palms – Mar Vista – Del Rey. You can select any filing below to calculate its 60-day statutory deadline and prepare a written status request.
| Permit number | Address | Submitted | Status | Elapsed | Declared value |
|---|---|---|---|---|---|
| 25010-20001-04543SUPPLEMENTAL PERMIT TO 25010 - 20000 - 04543 TO REVISE PLANS AND CORRECT HEIGHT PER SURVEY TO BE 24'-0" | 12569 1/2 W PRESNELL STZone R1-1 | Nov 13, 2026 | Issued | 0 days | $501 |
| 20014-30001-04394supplemental ref to pcis# 20014-10000-04394, to remove LID requirement. *** NO FEE DEPT. ERROR*** | 11872 W JUNIETTE STZone R1-1 | Nov 13, 2026 | Issued | 0 days | — |
| 25014-10001-03579Attention: Joseph Rafols - Supplemental Permit to 25014-10000-03579 to Remove rain barrel from the site plan & roof plan. | 12318 W STANWOOD DRZone R1V2 | Nov 5, 2026 | Issued | 6 days | $501 |
| 26014-30002-01427Supplemental to permit#: 26014-10000-01427 for "Revisions to structural plans". No change in inventory. | 3747 S ASHWOOD AVEZone R1V2 | Sep 21, 2026 | Issued | 0 days | $2,501 |
| 25014-10002-05030Supplemental to permit 25014-10000-05030 TO UPDATE ADU ADDRESS 3747 MOUNTAIN VIEW AVE | 3747 S MOUNTAIN VIEW AVEZone R1V2 | Sep 18, 2026 | Permit Finaled | 0 days | — |
| 25014-10002-02085Supplemental to 25014-10000-02085 to collect the additional school fees | 13143 W ROSE AVEZone R1V2 | Sep 17, 2026 | Permit Finaled | 0 days | — |
| 26014-30001-01427Supplemental ref to PCIS#: 26014-10000-01424 to "Revise structural plans and details". No change in inventory. | 3747 S ASHWOOD AVEZone R1V2 | Sep 15, 2026 | Issued | 0 days | $15,000 |
| 26014-10000-03354ePlan Addition to and convert (e) detached garage into ADU per LAMC 12.22 A.33(b)(1) | 11419 1/2 W CHARNOCK ROADZone R1V2 | Sep 9, 2026 | Issued | 35 days | $90,000 |
| 26016-10001-06580ePlan: Supplemental permit to permit #26016-10000-06580 to revise floor plan layout. No change in plot plan. | 12823 W GILMORE AVEZone R1-1 | Sep 8, 2026 | Issued | 6 days | $5,000 |
| 26010-20000-04576NEW (IRREGULAR SHAPED) DETACHED ACCESSORY DWELLING UNIT PER GCS 66323(a)(2). | 3973 S MICHAEL AVEZone R1V2 | Sep 4, 2026 | Issued | 33 days | $115,000 |
| 26014-10000-03387ePlan: ADDITION TO DETACHED ADU AND CONVERT DETACHED ADU FROM ORDINANCE ADU TO STATE LAW ADU. NO CHANGE IN UNIT COUNT. NO CHANGE OF OCCUPANCY. | 4104 S ALLA ROADZone R1-1 | Sep 2, 2026 | Issued | 37 days | $6,165 |
| 20016-10002-05548SUPPLEMENTAL TO 20016-30000-05548 TO OMIT "NFPA13D FIRE SPRINKLERS" FROM WORK DESCRIPTION AND INVENTORY.. | 3762 S MOORE STZone R1V2 | Sep 2, 2026 | Issued | 19 days | $2,501 |
| 25014-10001-05030Supplemental to permit 25014-10000-05030. REVISE PLAN TO INCLUDE NEW ADU ADDRESS 3747 MOUNTAIN VIEW AVE | 3745-3747 S MOUNTAIN VIEW AVEZone R1V2 | Sep 2, 2026 | Permit Finaled | 8 days | $501 |
| 26014-30000-03292Addition to and conversion of existing rec-room to ADU with attached trellis per GCS 66323 (a)(2) and attach existing garage to proposed ADU. Work per engineer. | 4274 S NEOSHO AVEZone R1-1 | Aug 26, 2026 | Issued | 28 days | $80,000 |
| 26016-10000-22618Convert portion of (E) SFD to a 484 sf JADU per GC 66323(a)(1). Remodel to (E) SFD. | 12600-12600 1/2 W APPLETON WAYZone R1V2 | Aug 25, 2026 | Issued | 42 days | $50,000 |
Check a Los Angeles building permit live
Search any permit number or street address in the City of Los Angeles Open Data registry. Your address stays in this browser tab and is never added to a link or stored.
60-day ADU shot-clock calculator & written notice
California Government Code § 66317 gives local permitting agencies 60 calendar days to ministerially approve or deny a complete Accessory Dwelling Unit application. Enter your application details below to calculate your statutory deadline and assemble a plain written status request for Palms – Mar Vista – Del Rey, Los Angeles.
- Submittal date
- November 23, 2026
- Day 45 check-in
- January 7, 2027
- Day 60 statutory deadline
- January 22, 2027
- Current status
- 60 days remaining in the 60-day window
Review written notice to LADBS Plan Check Supervisor
November 23, 2026
To: Plan Check Supervisor
Los Angeles Department of Building and Safety (LADBS)
201 N. Figueroa Street, Los Angeles, CA 90012
CC: California Department of Housing and Community Development (HCD) Housing Accountability Unit
Subject: Request for Ministerial ADU Review Status & Consolidated Corrections Under CA Gov. Code § 66317 — Permit #[PERMIT APPLICATION NUMBER]
Dear Plan Check Supervisor,
I am writing regarding Accessory Dwelling Unit (ADU) Permit Application #[PERMIT APPLICATION NUMBER] for [PROPERTY STREET ADDRESS, LOS ANGELES, CA], submitted on November 23, 2026.
Under California Government Code § 66317, the 60-day ministerial review window for a complete ADU application runs through January 22, 2027.
Pursuant to California Government Code § 66317, I respectfully request:
1. Immediate ministerial approval of this complete ADU application, OR
2. A single, complete, written set of objective code comments citing the exact code section for every remaining item so that all corrections can be resolved without serial plan-check cycles.
Please respond in writing with the current plan-check status, assigned plan checker, and next action date.
Sincerely,
[YOUR FULL NAME]
Permit Reference: #[PERMIT APPLICATION NUMBER]
Property Address: [PROPERTY STREET ADDRESS, LOS ANGELES, CA]
Election.org publishes official City of Los Angeles permit data and California statutory references for public accountability and citizen self-help. This draft is informational and is not legal representation; review every detail before sending.
Other Los Angeles Community Plan Areas
- West Adams – Baldwin Hills – Leimert, Los Angeles2,613 issued ADUs · 204 days average · 67% over 60 days
- South Los Angeles, Los Angeles2,603 issued ADUs · 217 days average · 72% over 60 days
- Northeast Los Angeles, Los Angeles2,334 issued ADUs · 229 days average · 69% over 60 days
- Wilshire, Los Angeles2,286 issued ADUs · 197 days average · 68% over 60 days
- Reseda – West Van Nuys, Los Angeles2,025 issued ADUs · 155 days average · 63% over 60 days
- Canoga Park – West Hills – Winnetka – Woodland Hills, Los Angeles2,021 issued ADUs · 155 days average · 60% over 60 days
Up: All Los Angeles permit timelines, Los Angeles officials, Local government
Sources & notes
Permit registryCity of Los Angeles Department of Building and Safety (LADBS) via City of Los Angeles Open Data
Open data endpointdata.lacity.org/resource/pi9x-tg5x.json
StatuteCalifornia Government Code § 66317 (60-day ministerial ADU review)
Data updatedNov 14, 2026