San Pedro, Los Angeles: ADU permit timelines
Across 250 issued Accessory Dwelling Unit permits in San Pedro, applications averaged 270 calendar days (80 days longer than the Los Angeles citywide average of 190 days), with 72% exceeding California’s 60-day review window under Gov. Code § 66317.
- 6,142 total LADBS permits in area
- 250 issued ADUs
- 181 ADUs over 60 days
- Updated Nov 14, 2026
Compare all 15 Los Angeles Council districts
Computed from City of Los Angeles Department of Building and Safety (LADBS) submittal and issuance dates in Los Angeles Open Data.
From City of Los Angeles Open Data (LADBS), as of November 14, 2026.
- Issued ADUs measured
- 250
- Average wait
- 270 days
- Over 60-day statutory window
- 72%
- Declared ADU valuation
- $16.0 million
Recent ADU permit filings in San Pedro
The 15 most recently submitted Accessory Dwelling Unit filings recorded by LADBS in San Pedro. You can select any filing below to calculate its 60-day statutory deadline and prepare a written status request.
| Permit number | Address | Submitted | Status | Elapsed | Declared value |
|---|---|---|---|---|---|
| 23010-10002-00702SUPPLEMENTAL PERMIT TO 23010-10000-00702 TO CHANGE SCOPE OF WORK FROM "CONVERT (E) SINGLE FAMILY DWELLING AND ATTACHED GARAGE TO A DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A | 1143 W 21ST STZone R1-1XL | Sep 24, 2026 | Issued | 0 days | — |
| 24010-10002-05041ePlan: SUPPLEMENTAL PERMIT TO 24010-10000-05041 TO REVISE TITLE 24 ANALYSIS TO NATURAL GAS. | 759 W 6TH STZone RD1.5-1XL | Aug 24, 2026 | Issued | 10 days | $2,500 |
| 26014-10001-00676ePlan: Supplemental #26014-10000-00676 to revise plans and clarify Addtion From 100 S.F. to 116 S.F on 1st Floor. | 1323-1323 1/2 W SILVIUS AVEZone R1-1XL | Aug 21, 2026 | IssuedExceeds 60-day law | 72 days | $6,060 |
| 25010-10001-01648eplan. Supplemental permit to 25010-10000-01648 to update height of building | 1367 W 1ST STZone R1-1XL | Aug 15, 2026 | Issued | 9 days | — |
| 26016-10000-18793ePlan. Convert (E) Detached Garage into an Accessory Dwelling Unit per GC 66323(a)(1) | 526 W 19TH STZone R2-1XL | Jul 16, 2026 | Issued | 32 days | $88,500 |
| 26010-10000-03068EPLAN: NEW ACCESORY DWELLING UNIT PER GCS 66323(a)(2). ALL WORK PER ENG. | 624 W 8TH STZone C2-2D-CPIO | Jul 3, 2026 | IssuedExceeds 60-day law | 131 days | $90,000 |
| 26010-10000-03128ePlan New 1 story detached ADU per LAMC 12.22.A.33 (b) and (1) with an attached 1 car garage. | 2162 W PASEO DEL MARZone R1-1XL | Jun 30, 2026 | IssuedExceeds 60-day law | 97 days | $200,000 |
| 25014-10001-03285Eplan. Supplemental permit to 25014-10000-03285 to remove fire sprinklers for new ADU. | 1506 S DODSON AVEZone R1-1XL | May 21, 2026 | Permit Finaled | 21 days | $501 |
| 25014-10001-02534SUPPLEMENTAL PERMIT TO #25014-40000-02534 FOR ALTERED ROOFS FROM HIPS TO SHEDS. BUILDING HEIGHT FROM 21' TO 23'. NFPA 13D- fire sprinkler thur-out. | 1705-1705 1/2 W EL REY ROADZone R1-1XL | May 8, 2026 | IssuedExceeds 60-day law | 74 days | $10,000 |
| 22010-10002-00355Supplemental permit for 22010-10000-00355 to recheck due to lost plan. | 785 W 29TH STZone R1-1XL | May 6, 2026 | IssuedExceeds 60-day law | 99 days | $501 |
| 24016-20002-34857SUPPLEMENTAL TO 24016-20000-34857 TO RELOCATE LAUNDRY TO GARAGE. ADD NEW EXTERIOR DOOR AT GARAGE. | 687-687 1/2 W 18TH STZone R2-1XL | May 1, 2026 | Issued | 19 days | $1,000 |
| 22010-10002-00356Supplemental permit for permit record 22010-10000-00356 to restamp the approved ePlan set due to the loss of the original paper-approved plans. | 910 W 29TH PLZone RD2-1XL | Apr 29, 2026 | IssuedExceeds 60-day law | 106 days | $501 |
| 25016-10001-04143SUPPLEMENTAL TO 25016-10000-04143 TO ADD A NEW WINDOW OPENING AND RELOCATED WASHER AND DRYER UNIT | 533 N ALBRO STZone R1-1XL | Apr 16, 2026 | Issued | 0 days | $1,000 |
| 26010-10000-01554EPLAN: NEW GROUND UP 1 STORY ADU (620 SF)( 1 OF 2) | 970 W OLIVER STZone R1-1XL | Apr 6, 2026 | IssuedExceeds 60-day law | 126 days | $70,000 |
| 23010-30001-05044Supplemental permit to # 23010-30000-05044 for interior kitchen layout changes | 665 W 11TH STZone RD1.5-1XL-CPIO | Mar 13, 2026 | Permit Finaled | 0 days | $501 |
Check a Los Angeles building permit live
Search any permit number or street address in the City of Los Angeles Open Data registry. Your address stays in this browser tab and is never added to a link or stored.
60-day ADU shot-clock calculator & written notice
California Government Code § 66317 gives local permitting agencies 60 calendar days to ministerially approve or deny a complete Accessory Dwelling Unit application. Enter your application details below to calculate your statutory deadline and assemble a plain written status request for San Pedro, Los Angeles.
- Submittal date
- November 23, 2026
- Day 45 check-in
- January 7, 2027
- Day 60 statutory deadline
- January 22, 2027
- Current status
- 60 days remaining in the 60-day window
Review written notice to LADBS Plan Check Supervisor
November 23, 2026
To: Plan Check Supervisor
Los Angeles Department of Building and Safety (LADBS)
201 N. Figueroa Street, Los Angeles, CA 90012
CC: California Department of Housing and Community Development (HCD) Housing Accountability Unit
Subject: Request for Ministerial ADU Review Status & Consolidated Corrections Under CA Gov. Code § 66317 — Permit #[PERMIT APPLICATION NUMBER]
Dear Plan Check Supervisor,
I am writing regarding Accessory Dwelling Unit (ADU) Permit Application #[PERMIT APPLICATION NUMBER] for [PROPERTY STREET ADDRESS, LOS ANGELES, CA], submitted on November 23, 2026.
Under California Government Code § 66317, the 60-day ministerial review window for a complete ADU application runs through January 22, 2027.
Pursuant to California Government Code § 66317, I respectfully request:
1. Immediate ministerial approval of this complete ADU application, OR
2. A single, complete, written set of objective code comments citing the exact code section for every remaining item so that all corrections can be resolved without serial plan-check cycles.
Please respond in writing with the current plan-check status, assigned plan checker, and next action date.
Sincerely,
[YOUR FULL NAME]
Permit Reference: #[PERMIT APPLICATION NUMBER]
Property Address: [PROPERTY STREET ADDRESS, LOS ANGELES, CA]
Election.org publishes official City of Los Angeles permit data and California statutory references for public accountability and citizen self-help. This draft is informational and is not legal representation; review every detail before sending.
Other Los Angeles Community Plan Areas
- West Adams – Baldwin Hills – Leimert, Los Angeles2,613 issued ADUs · 204 days average · 67% over 60 days
- South Los Angeles, Los Angeles2,603 issued ADUs · 217 days average · 72% over 60 days
- Northeast Los Angeles, Los Angeles2,334 issued ADUs · 229 days average · 69% over 60 days
- Wilshire, Los Angeles2,286 issued ADUs · 197 days average · 68% over 60 days
- Reseda – West Van Nuys, Los Angeles2,025 issued ADUs · 155 days average · 63% over 60 days
- Canoga Park – West Hills – Winnetka – Woodland Hills, Los Angeles2,021 issued ADUs · 155 days average · 60% over 60 days
Up: All Los Angeles permit timelines, Los Angeles officials, Local government
Sources & notes
Permit registryCity of Los Angeles Department of Building and Safety (LADBS) via City of Los Angeles Open Data
Open data endpointdata.lacity.org/resource/pi9x-tg5x.json
StatuteCalifornia Government Code § 66317 (60-day ministerial ADU review)
Data updatedNov 14, 2026