Sun Valley – La Tuna Canyon, Los Angeles: ADU permit timelines
Across 1,598 issued Accessory Dwelling Unit permits in Sun Valley – La Tuna Canyon, applications averaged 178 calendar days (12 days shorter than the Los Angeles citywide average of 190 days), with 62% exceeding California’s 60-day review window under Gov. Code § 66317.
- 8,473 total LADBS permits in area
- 1,598 issued ADUs
- 993 ADUs over 60 days
- Updated Nov 14, 2026
Compare all 15 Los Angeles Council districts
Computed from City of Los Angeles Department of Building and Safety (LADBS) submittal and issuance dates in Los Angeles Open Data.
From City of Los Angeles Open Data (LADBS), as of November 14, 2026.
- Issued ADUs measured
- 1,598
- Average wait
- 178 days
- Over 60-day statutory window
- 62%
- Declared ADU valuation
- $112.2 million
Recent ADU permit filings in Sun Valley – La Tuna Canyon
The 15 most recently submitted Accessory Dwelling Unit filings recorded by LADBS in Sun Valley – La Tuna Canyon. You can select any filing below to calculate its 60-day statutory deadline and prepare a written status request.
| Permit number | Address | Submitted | Status | Elapsed | Declared value |
|---|---|---|---|---|---|
| 25010-30003-01207Supplemental to 25010-30000-01207to capture hieght change | 12319-12321 W ROSCOE BLVDZone RS-1 | Nov 3, 2026 | Issued | 0 days | $2,501 |
| 26010-20001-01694SUPPLEMENTAL PERMIT FOR 26010-20000-01694 TO REVISE TITLE 24 | 8500 N SHARP AVEZone RS-1 | Oct 20, 2026 | Issued | 7 days | $2,501 |
| 25016-20001-33294SUPPLEMENTAL TO PERMIT 25016-20000-33294:REVISE INTERIOR LAYOUT AT BATHROOM AND LIVING/KITCHEN/DINNING AREA, (E) LAUNDRY TO REMIAN, (E) SHEAR WALLS AND OPENINGS TO REMAIN. NO CHAN | 1115 W LEADWELL STZone R1-1 | Oct 14, 2026 | Issued | 5 days | $10,000 |
| 26014-10001-02334SUPPLEMENTAL PERMIT TO 26014-20000-02334 TO REVISE CEILING JOIST DIRECTION AND FRAMING. | 10515 1/2 W LANARK STZone R1-1 | Oct 6, 2026 | Issued | 0 days | $501 |
| 26014-20000-03778CONVERT EXISTING DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER GCS 66323(a)(2) W/ ADDITION & ALL NEW ROOF FRAMING. ALL WORK PER WFPP. | 10912 W STRATHERN STZone R1-1 | Oct 2, 2026 | Issued | 35 days | $70,000 |
| 26014-20000-03734CONVERT (E) GARAGE TO STORAGE ROOM AND ADD ACCESSORY DWELLING UNIT TO (E) SFD PER GCS 66323(a)(1) | 10923-10925 W GOSS STZone R1-1-CUGU | Sep 29, 2026 | Issued | 10 days | $50,197 |
| 25010-30002-01450SUPPLEMENTAL TO 25010-20000-01450 TO REVISE COVER SHEET TO REFLECT CORRECTED MAX HEIGHT AND UPDATE INVENTORY. | 7626 N GREG AVEZone R1-1 | Sep 29, 2026 | Issued | 0 days | $2,501 |
| 26016-20000-25355CONVERT SINGLE FAMILY DWELLING AND UNPERMITTED ADDITION TO ACCESSORY DWELLING UNIT (1074 SQ FT) PER GCS 66314-66331 | 8040 N TROOST AVEZone R1-1-CUGU | Sep 24, 2026 | Issued | 14 days | $75,000 |
| 21016-20001-55548SUPPLEMENTAL PERMIT TO 21016-20000-55548 TO RENEW THE EXPIRED PERMIT AT 80% COMPLETED | 7708 N WILKINSON AVEZone R1-1 | Sep 24, 2026 | Permit Finaled | 0 days | $5,000 |
| 26014-20000-02876EXISTING GARAGE CONVERSION TO NEW 1 STORY DETACHED ADU PER GC66323(a)(2) | 7560 N DELIA AVEZone R1-1 | Sep 22, 2026 | Issued | 28 days | $50,000 |
| 26016-20000-25592ePlan: Convert (E) detached Garage to Acessory Dwelling Unit per state law govt code section 66323(a)(1) . Work per engineered design . | 13112 W ROSCOE BLVDZone R1-1 | Sep 21, 2026 | Issued | 16 days | $35,000 |
| 25014-20002-03194SUPPLEMENTAL TO PERMIT# 25014-20000-03194 TO REVISE STRUCTURAL FRAMING PLANS. | 12763-12763 1/2 W ELKWOOD STZone R1-1 | Sep 17, 2026 | Issued | 0 days | $2,500 |
| 26014-20000-03584ADDITION TO THE (E) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1)3 | 8214 N RHODES AVEZone RS-1 | Sep 17, 2026 | Issued | 53 days | $35,000 |
| 26016-20000-24157CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 66323(A)(1) | 8420 N GLENCREST DRZone R1-1 | Sep 8, 2026 | Issued | 52 days | $25,000 |
| 26016-20000-24138PERMIT PREVIOUSLY UNPERMITTED CONVERSION OF PORTION OF EXISTING 1-STORY GARAGE TO AN ACCESSORY DWELLLING UNIT PER AB 2533 & REMAINING PORTION INTO STORAGE ROOM (ACCESSIBLE FROM OUT | 10818 W CROCKETT STZone R1-1 | Sep 8, 2026 | Issued | 30 days | $70,000 |
Check a Los Angeles building permit live
Search any permit number or street address in the City of Los Angeles Open Data registry. Your address stays in this browser tab and is never added to a link or stored.
60-day ADU shot-clock calculator & written notice
California Government Code § 66317 gives local permitting agencies 60 calendar days to ministerially approve or deny a complete Accessory Dwelling Unit application. Enter your application details below to calculate your statutory deadline and assemble a plain written status request for Sun Valley – La Tuna Canyon, Los Angeles.
- Submittal date
- November 23, 2026
- Day 45 check-in
- January 7, 2027
- Day 60 statutory deadline
- January 22, 2027
- Current status
- 60 days remaining in the 60-day window
Review written notice to LADBS Plan Check Supervisor
November 23, 2026
To: Plan Check Supervisor
Los Angeles Department of Building and Safety (LADBS)
201 N. Figueroa Street, Los Angeles, CA 90012
CC: California Department of Housing and Community Development (HCD) Housing Accountability Unit
Subject: Request for Ministerial ADU Review Status & Consolidated Corrections Under CA Gov. Code § 66317 — Permit #[PERMIT APPLICATION NUMBER]
Dear Plan Check Supervisor,
I am writing regarding Accessory Dwelling Unit (ADU) Permit Application #[PERMIT APPLICATION NUMBER] for [PROPERTY STREET ADDRESS, LOS ANGELES, CA], submitted on November 23, 2026.
Under California Government Code § 66317, the 60-day ministerial review window for a complete ADU application runs through January 22, 2027.
Pursuant to California Government Code § 66317, I respectfully request:
1. Immediate ministerial approval of this complete ADU application, OR
2. A single, complete, written set of objective code comments citing the exact code section for every remaining item so that all corrections can be resolved without serial plan-check cycles.
Please respond in writing with the current plan-check status, assigned plan checker, and next action date.
Sincerely,
[YOUR FULL NAME]
Permit Reference: #[PERMIT APPLICATION NUMBER]
Property Address: [PROPERTY STREET ADDRESS, LOS ANGELES, CA]
Election.org publishes official City of Los Angeles permit data and California statutory references for public accountability and citizen self-help. This draft is informational and is not legal representation; review every detail before sending.
Other Los Angeles Community Plan Areas
- West Adams – Baldwin Hills – Leimert, Los Angeles2,613 issued ADUs · 204 days average · 67% over 60 days
- South Los Angeles, Los Angeles2,603 issued ADUs · 217 days average · 72% over 60 days
- Northeast Los Angeles, Los Angeles2,334 issued ADUs · 229 days average · 69% over 60 days
- Wilshire, Los Angeles2,286 issued ADUs · 197 days average · 68% over 60 days
- Reseda – West Van Nuys, Los Angeles2,025 issued ADUs · 155 days average · 63% over 60 days
- Canoga Park – West Hills – Winnetka – Woodland Hills, Los Angeles2,021 issued ADUs · 155 days average · 60% over 60 days
Up: All Los Angeles permit timelines, Los Angeles officials, Local government
Sources & notes
Permit registryCity of Los Angeles Department of Building and Safety (LADBS) via City of Los Angeles Open Data
Open data endpointdata.lacity.org/resource/pi9x-tg5x.json
StatuteCalifornia Government Code § 66317 (60-day ministerial ADU review)
Data updatedNov 14, 2026