Sylmar, Los Angeles: ADU permit timelines
Across 694 issued Accessory Dwelling Unit permits in Sylmar, applications averaged 174 calendar days (16 days shorter than the Los Angeles citywide average of 190 days), with 63% exceeding California’s 60-day review window under Gov. Code § 66317.
- 5,149 total LADBS permits in area
- 694 issued ADUs
- 438 ADUs over 60 days
- Updated Nov 14, 2026
Compare all 15 Los Angeles Council districts
Computed from City of Los Angeles Department of Building and Safety (LADBS) submittal and issuance dates in Los Angeles Open Data.
From City of Los Angeles Open Data (LADBS), as of November 14, 2026.
- Issued ADUs measured
- 694
- Average wait
- 174 days
- Over 60-day statutory window
- 63%
- Declared ADU valuation
- $44.1 million
Recent ADU permit filings in Sylmar
The 15 most recently submitted Accessory Dwelling Unit filings recorded by LADBS in Sylmar. You can select any filing below to calculate its 60-day statutory deadline and prepare a written status request.
| Permit number | Address | Submitted | Status | Elapsed | Declared value |
|---|---|---|---|---|---|
| 20014-20003-01667SUPPL. PERMIT TO 20014-10000-01667 TO REVISE TITLE 24 | 13416 W HERRON STZone R1-1 | Nov 13, 2026 | Issued | 0 days | $2,501 |
| 24016-20003-40197SUPPLEMENTAL PERMIT TO 24016-20000-40197 TO UPDATE STRUCTURAL INVENTORY*NO FEE DEPT ERROR* | 12600-12602 N AMBOY AVEZone RS-1 | Nov 4, 2026 | Permit Finaled | 0 days | — |
| 24016-20002-40197EPLAN: Supplemental permit to 24016-20000-40197 to update work descirption to CONVERT EXISTING ATTACHED GARAGE TO ADU PER GCS 66323(a)(1)) PER WFPP.*NO FEE DEPT ERROR* | 12600-12602 N AMBOY AVEZone RS-1 | Oct 13, 2026 | Permit Finaled | 0 days | — |
| 22014-20002-03516SUPPLEMENTAL PERMIT TO 22014-20000-03516 TO REVISE THE FLOOR AND STRUCTURAL PLANS. REMOVE (E) ATTACHED PATIO COVER. | 14259 W HUBBARD STZone R1-1 | Oct 1, 2026 | Issued | 4 days | $2,501 |
| 26014-10000-03756REAR ADDITION AND REMODEL OF SFD WITH ATTACHED GARAGED FOR NEW MASTER BEDROOM AND ATTACHED ADU PER ORDINANCE | 14322-14324 W BEAVER STZone R1-1 | Sep 30, 2026 | Issued | 35 days | $93,000 |
| 26014-20001-02881Eplan. Supplemental permit to 26014-20000-02881 to enlarge proposed ADU. | 13511 W SAYRE STZone R1-1 | Sep 22, 2026 | Issued | 16 days | $40,000 |
| 26016-20001-12770SUPPL. PERMIT TO 26016-20000-12770 TO REVISE THE (E) TO (N) FOOTING CONNECTION DETAILS. | 12579 N BROMONT AVEZone R1-1 | Sep 15, 2026 | Issued | 2 days | $2,501 |
| 23014-10001-04846Supplemental to 23014-10000-04846 to collect the additional school fees | 13281 N HERRICK AVEZone RS-1 | Sep 14, 2026 | Permit Finaled | 0 days | — |
| 26016-20000-24650CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 66323(a)(1) AND CONVERT PORTION OF (E) SINGLE FAMILY DWELLING TO 391 SQ FT JUNIOR ACCESSORY DWELLING UNIT PER GCS 663 | 13184-13188 W LEACH STZone R1-1 | Sep 11, 2026 | Issued | 17 days | $20,000 |
| 26014-20000-03305EPLAN - ADDITION AND CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GC 66323(a)(2). ALL WORK PER WFPP | 13391 W BERG STZone R1-1 | Sep 2, 2026 | IssuedExceeds 60-day law | 64 days | $105,000 |
| 25010-20001-04171SUPPLEMENTAL FOR 25010 - 20000 - 04171ROTATE THE ADU 90 DEGREES | 15442 W ROXFORD STZone RA-1-K | Aug 27, 2026 | Issued | 15 days | $2,501 |
| 25010-20001-05188SUPPLEMENTAL TO PERMIT# 25010-20000-05188TO UPDATE THE SETBACKS PER THE SURVEY AND THE LOCATION OF THE WATER HEATER AND THE AC CONDENSER | 12949 W ROMONT STZone RS-1 | Aug 24, 2026 | Issued | 18 days | $2,501 |
| 23010-10001-05278SUPPLEMENTAL PERMIT TO PERMIT#23010-20000-05278 FOR REVISIONS TO SETBACKS AND FIRE RATED EAVE DETAIL. | 12564 N COMETA AVEZone R1-1 | Aug 21, 2026 | Issued | 5 days | $501 |
| 25016-10002-28458No Fee Dept Error . Supplemental to 25016-10000-28458 to revise structural inventory . (No change in plot plan) . | 13751 N DE GARMO AVE #1-3Zone RA-1-K | Aug 21, 2026 | Permit Finaled | 0 days | $501 |
| 26014-20000-03194ADDITION TO AND CONVERT (E) GARAGE TO ACCESSORY DWELLING UNIT PER GC 66323(a)(1). ADDITION OF BREEZEWAY TO ATTACH ACCESSORY DWELLING UNIT TO (E) SFD. | 15131-15131 1/2 W POLK STZone RE9-1 | Aug 18, 2026 | Issued | 17 days | $78,000 |
Check a Los Angeles building permit live
Search any permit number or street address in the City of Los Angeles Open Data registry. Your address stays in this browser tab and is never added to a link or stored.
60-day ADU shot-clock calculator & written notice
California Government Code § 66317 gives local permitting agencies 60 calendar days to ministerially approve or deny a complete Accessory Dwelling Unit application. Enter your application details below to calculate your statutory deadline and assemble a plain written status request for Sylmar, Los Angeles.
- Submittal date
- November 23, 2026
- Day 45 check-in
- January 7, 2027
- Day 60 statutory deadline
- January 22, 2027
- Current status
- 60 days remaining in the 60-day window
Review written notice to LADBS Plan Check Supervisor
November 23, 2026
To: Plan Check Supervisor
Los Angeles Department of Building and Safety (LADBS)
201 N. Figueroa Street, Los Angeles, CA 90012
CC: California Department of Housing and Community Development (HCD) Housing Accountability Unit
Subject: Request for Ministerial ADU Review Status & Consolidated Corrections Under CA Gov. Code § 66317 — Permit #[PERMIT APPLICATION NUMBER]
Dear Plan Check Supervisor,
I am writing regarding Accessory Dwelling Unit (ADU) Permit Application #[PERMIT APPLICATION NUMBER] for [PROPERTY STREET ADDRESS, LOS ANGELES, CA], submitted on November 23, 2026.
Under California Government Code § 66317, the 60-day ministerial review window for a complete ADU application runs through January 22, 2027.
Pursuant to California Government Code § 66317, I respectfully request:
1. Immediate ministerial approval of this complete ADU application, OR
2. A single, complete, written set of objective code comments citing the exact code section for every remaining item so that all corrections can be resolved without serial plan-check cycles.
Please respond in writing with the current plan-check status, assigned plan checker, and next action date.
Sincerely,
[YOUR FULL NAME]
Permit Reference: #[PERMIT APPLICATION NUMBER]
Property Address: [PROPERTY STREET ADDRESS, LOS ANGELES, CA]
Election.org publishes official City of Los Angeles permit data and California statutory references for public accountability and citizen self-help. This draft is informational and is not legal representation; review every detail before sending.
Other Los Angeles Community Plan Areas
- West Adams – Baldwin Hills – Leimert, Los Angeles2,613 issued ADUs · 204 days average · 67% over 60 days
- South Los Angeles, Los Angeles2,603 issued ADUs · 217 days average · 72% over 60 days
- Northeast Los Angeles, Los Angeles2,334 issued ADUs · 229 days average · 69% over 60 days
- Wilshire, Los Angeles2,286 issued ADUs · 197 days average · 68% over 60 days
- Reseda – West Van Nuys, Los Angeles2,025 issued ADUs · 155 days average · 63% over 60 days
- Canoga Park – West Hills – Winnetka – Woodland Hills, Los Angeles2,021 issued ADUs · 155 days average · 60% over 60 days
Up: All Los Angeles permit timelines, Los Angeles officials, Local government
Sources & notes
Permit registryCity of Los Angeles Department of Building and Safety (LADBS) via City of Los Angeles Open Data
Open data endpointdata.lacity.org/resource/pi9x-tg5x.json
StatuteCalifornia Government Code § 66317 (60-day ministerial ADU review)
Data updatedNov 14, 2026