Westchester – Playa del Rey, Los Angeles: ADU permit timelines

Across 685 issued Accessory Dwelling Unit permits in Westchester – Playa del Rey, applications averaged 188 calendar days (2 days shorter than the Los Angeles citywide average of 190 days), with 70% exceeding California’s 60-day review window under Gov. Code § 66317.

  • 9,126 total LADBS permits in area
  • 685 issued ADUs
  • 479 ADUs over 60 days
  • Updated Nov 14, 2026

Compare all 15 Los Angeles Council districts

Computed from City of Los Angeles Department of Building and Safety (LADBS) submittal and issuance dates in Los Angeles Open Data.

From City of Los Angeles Open Data (LADBS), as of November 14, 2026.

Issued ADUs measured
685
Average wait
188 days
Over 60-day statutory window
70%
Declared ADU valuation
$47.1 million

Recent ADU permit filings in Westchester – Playa del Rey

The 15 most recently submitted Accessory Dwelling Unit filings recorded by LADBS in Westchester – Playa del Rey. You can select any filing below to calculate its 60-day statutory deadline and prepare a written status request.

Recent LADBS Accessory Dwelling Unit filings in Westchester – Playa del Rey, Los Angeles
Permit numberAddressSubmittedStatusElapsedDeclared value
26014-10001-00224Supplemental permit to 26014-10000-00224 to capture MEP fees8129 S WESTLAWN AVEZone R1V2Nov 13, 2026Issued0 days$3,000
25016-10001-06927SUPPLEMENTAL TO PERMIT#25016-10000-06927 TO REVISE THE BUILDING SUBTYPE FROMAPARTMENT TO SFD/DUPLEX AND CAPTURE MEP WORK.9007 3/4-5/8 S RAMSGATE AVEZone R3-1Sep 10, 2026Issued0 days$61,000
26014-30000-03189new detached 1-story ADU w/ attached garage PER GC 66323(a)(2)6031 W WILL ROGERS STZone R1-1Aug 18, 2026Issued50 days$150,000
26016-10000-21629ePlan: ANCHOR FOR ROOF MOUNTED SOLAR PV ON (E) ACCESSORY DWELING UNIT.6642 W 83RD STZone R1V2Aug 14, 2026IssuedExceeds 60-day law62 days$10,000
22010-20001-05435SUPP TO PERMIT 22010-20000-05435 TO REVISE THE SITE PLAN, AND REVISE BLDG WIDTH TO 14' IN WORK DESCRIPTION & STR INVENTORY8903 S KITTYHAWK AVEZone R1-1Aug 14, 2026Issued0 days$2,500
26016-10000-21292Eplan: CONVERT EXISTING GARAGE TO CREATE NEW 365 SF ADU. PER GC 66323(a)(1).7373 W 82ND STZone R1-1Aug 12, 2026Issued55 days$35,000
25014-10001-00126EPLAN: SUPPLEMENTAL TO PERMIT #25014-10000-00126 TO REVISE BATHROOM AND LAUNDRY ROOM LAYOUT (NO CHANGE TO BLDG DIM AND HEIGHT)7923 S AIRPORT BLVDZone RD2-1Aug 6, 2026Issued21 days$1,000
26014-20000-0300311'-11" X 7'-0" ADDITION TO (E) DETACHED GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT PER GCS 66323(a)(2).7909 S VICKSBURG AVEZone R1-1Aug 4, 2026Issued52 days$65,000
24014-10001-05281ePLANSUPPLEMENTAL PERMIT TO 24014-10000-05281 TO REVISE STRUCTURAL PLANS8319 S HOLY CROSS PLZone R1-1Jul 29, 2026Issued6 days$1,000
25010-10001-03160Supplemental permit to 25010-10000-03160 to revised to vaulted ceiling, height and alter openings.7309 W 87TH PLZone R1-1Jul 28, 2026Issued35 days$2,501
24014-10002-04868SUPPLEMENTAL TO 24014-10000-04868 1)REMOVING THE PREVIOUS PERGOLA FROM THIS SCOPE OF WORK. 2)UPDATING THE WINDOWS & ADU ENTRANCE DOOR.NO CHANGES TO PLOT PLAN7435 S ARIZONA AVEZone R1V2Jul 28, 2026Issued8 days$3,000
26010-10000-03846ePLANCONVERT EXISTING ATTACHED GARAGE AND WORKSHOP INTO AN ATTACHED ACCESSORY DWELLING UNIT (ADU) PER GC 66323(a)(1)7012-7014 S RAMSGATE AVEZone R1-1Jul 22, 2026Issued28 days$50,000
26014-10000-02802eplan New Attached Accessory Dwelling Unit (ADU) per LAMC 12.22 A.33(C) AND (E) and main house remodel8036-8038 S REGIS WAYZone R1-1Jul 21, 2026IssuedExceeds 60-day law66 days$70,000
26016-30000-18760Garage conversion into an ADU PER GC 66323 (a)(1)7829 S AGNEW AVEZone R1V2Jul 16, 2026IssuedExceeds 60-day law117 days$50,000
26014-10000-02721CONVERT (E) DETACHED GARAGE WITH NEW ADDITION TO AN ACCESSORY DWELLING UNIT PER GC 66323(a)(2) AND ADD NEW STORAGE.6463 W 87TH PLZone R1-1Jul 16, 2026IssuedExceeds 60-day law81 days$80,000

Check a Los Angeles building permit live

Search any permit number or street address in the City of Los Angeles Open Data registry. Your address stays in this browser tab and is never added to a link or stored.

60-day ADU shot-clock calculator & written notice

California Government Code § 66317 gives local permitting agencies 60 calendar days to ministerially approve or deny a complete Accessory Dwelling Unit application. Enter your application details below to calculate your statutory deadline and assemble a plain written status request for Westchester – Playa del Rey, Los Angeles.

Submittal date
November 23, 2026
Day 45 check-in
January 7, 2027
Day 60 statutory deadline
January 22, 2027
Current status
60 days remaining in the 60-day window
Review written notice to LADBS Plan Check Supervisor

November 23, 2026

To: Plan Check Supervisor
Los Angeles Department of Building and Safety (LADBS)

201 N. Figueroa Street, Los Angeles, CA 90012

CC: California Department of Housing and Community Development (HCD) Housing Accountability Unit

Subject: Request for Ministerial ADU Review Status & Consolidated Corrections Under CA Gov. Code § 66317 — Permit #[PERMIT APPLICATION NUMBER]

Dear Plan Check Supervisor,

I am writing regarding Accessory Dwelling Unit (ADU) Permit Application #[PERMIT APPLICATION NUMBER] for [PROPERTY STREET ADDRESS, LOS ANGELES, CA], submitted on November 23, 2026.

Under California Government Code § 66317, the 60-day ministerial review window for a complete ADU application runs through January 22, 2027.

Pursuant to California Government Code § 66317, I respectfully request:
1. Immediate ministerial approval of this complete ADU application, OR

2. A single, complete, written set of objective code comments citing the exact code section for every remaining item so that all corrections can be resolved without serial plan-check cycles.

Please respond in writing with the current plan-check status, assigned plan checker, and next action date.

Sincerely,
[YOUR FULL NAME]

Permit Reference: #[PERMIT APPLICATION NUMBER]

Property Address: [PROPERTY STREET ADDRESS, LOS ANGELES, CA]

Informational public-record tool

Election.org publishes official City of Los Angeles permit data and California statutory references for public accountability and citizen self-help. This draft is informational and is not legal representation; review every detail before sending.

Other Los Angeles Community Plan Areas

Sources & notes

Report a problem with this record

Help build better election infrastructureIndependent. Public. Powered by you.
Donate
Help build better election infrastructure

We at Election.org want to build the best election infrastructure and need your help.

Choose an amount Secure checkout through Stripe.