Westlake, Los Angeles: ADU permit timelines
Across 107 issued Accessory Dwelling Unit permits in Westlake, applications averaged 283 calendar days (93 days longer than the Los Angeles citywide average of 190 days), with 73% exceeding California’s 60-day review window under Gov. Code § 66317.
- 3,291 total LADBS permits in area
- 107 issued ADUs
- 78 ADUs over 60 days
- Updated Nov 14, 2026
Compare all 15 Los Angeles Council districts
Computed from City of Los Angeles Department of Building and Safety (LADBS) submittal and issuance dates in Los Angeles Open Data.
From City of Los Angeles Open Data (LADBS), as of November 14, 2026.
- Issued ADUs measured
- 107
- Average wait
- 283 days
- Over 60-day statutory window
- 73%
- Declared ADU valuation
- $7.5 million
Recent ADU permit filings in Westlake
The 15 most recently submitted Accessory Dwelling Unit filings recorded by LADBS in Westlake. You can select any filing below to calculate its 60-day statutory deadline and prepare a written status request.
| Permit number | Address | Submitted | Status | Elapsed | Declared value |
|---|---|---|---|---|---|
| 25014-20001-03555NO FEE DEPT. ERROR - SUPPLEMENTAL PERMIT TO 25014 - 20000 -03555 TO CORRECT PERMIT SUB-TYPE TO "APARTMENT" | 224-224 1/2 S BONNIE BRAE STZone R4-1 | Aug 21, 2026 | Issued | 0 days | — |
| 26010-20000-02660NEW TWO STORY BUILDING CONTAINING TWO ACCESSORY DWELLING UNITS ON TOP OF EACH OTHER PER GC 66323(a)(4) - PER ENGINEER *NFPA-13D FIRE SPRINKLERED THROUGHOUT | 2339-2339 1/8 W MIRAMAR STZone R3-1 | Jun 3, 2026 | IssuedExceeds 60-day law | 125 days | $100,000 |
| 26010-20000-02662NEW TWO STORY BUILDING CONTAINING TWO ACCESSORY DWELLING UNITS ON TOP OF EACH OTHER PER GC 66323(a)(4) - PER ENGINEER *NFPA-13D FIRE SPRINKLERED THROUGHOUT | 2339 1/2-5/8 W MIRAMAR STZone R3-1 | Jun 3, 2026 | IssuedExceeds 60-day law | 125 days | $100,000 |
| 26010-20000-02666NEW TWO STORY BUILDING CONTAINING TWO ACCESSORY DWELLING UNITS ON TOP OF EACH OTHER PER GC 66323(a)(4) - PER ENGINEER *NFPA-13D FIRE SPRINKLERED THROUGHOUT | 2342 W VALLEY ST 1-2Zone R3-1 | Jun 3, 2026 | IssuedExceeds 60-day law | 125 days | $65,000 |
| 26010-20000-02665NEW TWO STORY BUILDING CONTAINING TWO ACCESSORY DWELLING UNITS ON TOP OF EACH OTHER PER GC 66323(a)(4) - PER ENGINEER *NFPA-13D FIRE SPRINKLERED THROUGHOUT | 2340 W VALLEY ST 1-2Zone R3-1 | Jun 3, 2026 | IssuedExceeds 60-day law | 125 days | $65,000 |
| 26010-20000-02667NEW TWO STORY BUILDING CONTAINING TWO ACCESSORY DWELLING UNITS ON TOP OF EACH OTHER PER GC 66323(a)(4) - PER ENGINEER *NFPA-13D FIRE SPRINKLERED THROUGHOUT | 2338 W VALLEY ST 1-2Zone R3-1 | Jun 3, 2026 | IssuedExceeds 60-day law | 125 days | $65,000 |
| 26010-20000-02664NEW TWO STORY BUILDING CONTAINING TWO ACCESSORY DWELLING UNITS ON TOP OF EACH OTHER PER GC 66323(a)(4) - PER ENGINEER *NFPA-13D FIRE SPRINKLERED THROUGHOUT | 2336 W VALLEY ST 1-2Zone R3-1 | Jun 3, 2026 | IssuedExceeds 60-day law | 125 days | $65,000 |
| 26010-20000-02663NEW TWO STORY BUILDING CONTAINING TWO ACCESSORY DWELLING UNITS ON TOP OF EACH OTHER PER GC 66323(a)(4) - PER ENGINEER*NFPA-13D FIRE SPRINKLERED THROUGHOUT | 2339 3/4-7/8 W MIRAMAR STZone R3-1 | Jun 3, 2026 | IssuedExceeds 60-day law | 125 days | $100,000 |
| 26010-20000-02661NEW TWO STORY BUILDING CONTAINING TWO ACCESSORY DWELLING UNITS ON TOP OF EACH OTHER PER GC 66323(a)(4) - PER ENGINEER *NFPA-13D FIRE SPRINKLERED THROUGHOUT | 2339 1/4-3/8 W MIRAMAR STZone R3-1 | Jun 3, 2026 | IssuedExceeds 60-day law | 125 days | $100,000 |
| 24016-10002-37238supplemental to 24016-10000-37238 to clarify the sprinkler is only required throughout the garage and ADU since the sprinkler was only required for the gargae level per record 1988 | 816 S WESTLAKE AVE 1-22Zone R3-1 | Jun 2, 2026 | Permit Finaled | 0 days | $501 |
| 22010-10003-03792SUPPLEMENTAL PERMIT TO 22010-10000-03792 TO UPDATE THE ENGINEER AND ARCHITECT'S INFORMATION. | 1814 W COURT STZone RD1.5-1 | Apr 21, 2026 | Issued | 0 days | $2,500 |
| 23010-10006-00876SUPPLEMENTAL PERMIT TO PERMIT # 23010-10000-00876 TO REVISE FLOOR PLAN TO INCLUDE AN ADDITIONAL BATHROOM AND 1ST AND 3RD FLOOR OF THE REAR BUILDING. NO CHANGE TO THE SQUARE FOOTAGE | 130-130 1/4 N CARONDELET STZone RD1.5-1 | Feb 26, 2026 | Issued | 0 days | $501 |
| 25014-20000-05304NEW TWO STORY ACCESSORY DWELLING UNIT ADDITION TO EXISTING TRIPLEX PER LAMC 12.22.A.33 (c) AND (e) | 126-128 1/2 N VENDOME STZone RD1.5-1 | Dec 2, 2025 | IssuedExceeds 60-day law | 169 days | $90,000 |
| 22016-10002-10307Supplemental to 22016-10000-10307 due to change of ceiling design from vaulted ceiling to flat ceiling of second floor. | 1328 S WESTLAKE AVEZone RD1.5-1-HPOZ | Nov 19, 2025 | Permit Finaled | 37 days | $501 |
| 24014-10001-04120EPLAN: SUPPLEMENTAL PERMIT TO 24014-10000-04120 TO MODIFY FLOOR PLAN AND AREA OF PROPOSED ADUs | 1816-1816 1/2 W 12TH STZone RD1.5-1-HPOZ | Nov 13, 2025 | IssuedExceeds 60-day law | 102 days | $1,000 |
Check a Los Angeles building permit live
Search any permit number or street address in the City of Los Angeles Open Data registry. Your address stays in this browser tab and is never added to a link or stored.
60-day ADU shot-clock calculator & written notice
California Government Code § 66317 gives local permitting agencies 60 calendar days to ministerially approve or deny a complete Accessory Dwelling Unit application. Enter your application details below to calculate your statutory deadline and assemble a plain written status request for Westlake, Los Angeles.
- Submittal date
- November 23, 2026
- Day 45 check-in
- January 7, 2027
- Day 60 statutory deadline
- January 22, 2027
- Current status
- 60 days remaining in the 60-day window
Review written notice to LADBS Plan Check Supervisor
November 23, 2026
To: Plan Check Supervisor
Los Angeles Department of Building and Safety (LADBS)
201 N. Figueroa Street, Los Angeles, CA 90012
CC: California Department of Housing and Community Development (HCD) Housing Accountability Unit
Subject: Request for Ministerial ADU Review Status & Consolidated Corrections Under CA Gov. Code § 66317 — Permit #[PERMIT APPLICATION NUMBER]
Dear Plan Check Supervisor,
I am writing regarding Accessory Dwelling Unit (ADU) Permit Application #[PERMIT APPLICATION NUMBER] for [PROPERTY STREET ADDRESS, LOS ANGELES, CA], submitted on November 23, 2026.
Under California Government Code § 66317, the 60-day ministerial review window for a complete ADU application runs through January 22, 2027.
Pursuant to California Government Code § 66317, I respectfully request:
1. Immediate ministerial approval of this complete ADU application, OR
2. A single, complete, written set of objective code comments citing the exact code section for every remaining item so that all corrections can be resolved without serial plan-check cycles.
Please respond in writing with the current plan-check status, assigned plan checker, and next action date.
Sincerely,
[YOUR FULL NAME]
Permit Reference: #[PERMIT APPLICATION NUMBER]
Property Address: [PROPERTY STREET ADDRESS, LOS ANGELES, CA]
Election.org publishes official City of Los Angeles permit data and California statutory references for public accountability and citizen self-help. This draft is informational and is not legal representation; review every detail before sending.
Other Los Angeles Community Plan Areas
- West Adams – Baldwin Hills – Leimert, Los Angeles2,613 issued ADUs · 204 days average · 67% over 60 days
- South Los Angeles, Los Angeles2,603 issued ADUs · 217 days average · 72% over 60 days
- Northeast Los Angeles, Los Angeles2,334 issued ADUs · 229 days average · 69% over 60 days
- Wilshire, Los Angeles2,286 issued ADUs · 197 days average · 68% over 60 days
- Reseda – West Van Nuys, Los Angeles2,025 issued ADUs · 155 days average · 63% over 60 days
- Canoga Park – West Hills – Winnetka – Woodland Hills, Los Angeles2,021 issued ADUs · 155 days average · 60% over 60 days
Up: All Los Angeles permit timelines, Los Angeles officials, Local government
Sources & notes
Permit registryCity of Los Angeles Department of Building and Safety (LADBS) via City of Los Angeles Open Data
Open data endpointdata.lacity.org/resource/pi9x-tg5x.json
StatuteCalifornia Government Code § 66317 (60-day ministerial ADU review)
Data updatedNov 14, 2026