Westwood, Los Angeles: ADU permit timelines
Across 219 issued Accessory Dwelling Unit permits in Westwood, applications averaged 167 calendar days (23 days shorter than the Los Angeles citywide average of 190 days), with 65% exceeding California’s 60-day review window under Gov. Code § 66317.
- 6,148 total LADBS permits in area
- 219 issued ADUs
- 143 ADUs over 60 days
- Updated Nov 14, 2026
Compare all 15 Los Angeles Council districts
Computed from City of Los Angeles Department of Building and Safety (LADBS) submittal and issuance dates in Los Angeles Open Data.
From City of Los Angeles Open Data (LADBS), as of November 14, 2026.
- Issued ADUs measured
- 219
- Average wait
- 167 days
- Over 60-day statutory window
- 65%
- Declared ADU valuation
- $12.3 million
Recent ADU permit filings in Westwood
The 15 most recently submitted Accessory Dwelling Unit filings recorded by LADBS in Westwood. You can select any filing below to calculate its 60-day statutory deadline and prepare a written status request.
| Permit number | Address | Submitted | Status | Elapsed | Declared value |
|---|---|---|---|---|---|
| 25016-30005-37030Supplemental ref to pcis #25016-30000-37030, to voluntarily add angle braces to provide additional stiffness to the structure during the construction phase | 592-594 S MAPLETON DRZone RE40-1 | Oct 20, 2026 | Issued | 0 days | $2,501 |
| 26014-10000-02915EPLAN. CONVERSION OF AN EXISTING DETACHED GARAGE WITH ADDITION TO AN ADU PER GCS 66323(a)(1) | 11152 W SUNSET BLVDZone R1-1 | Jul 28, 2026 | IssuedExceeds 60-day law | 77 days | $100,000 |
| 24014-10002-02167Supplemental to 24014-10000-02167 to collect the additional school fees | 10754 W WELLWORTH AVEZone R1-1-O | Jul 21, 2026 | Issued | 0 days | — |
| 18010-30003-05830Supplemental permit to 18010-30000-05830 to change the address for ADU and change the fire sprinkler system requirement from NFPA 13R to NFPA 13D | 855 S COMSTOCK AVEZone R1-1 | May 18, 2026 | IssuedExceeds 60-day law | 77 days | $2,501 |
| 26010-20000-02112NEW 1-STORY DETACHED ACCESSORY DWELLING UNIT TO COMPLY WITH GCS 66323(a)(2) PER ENGINEERING. NFPA-13D FIRE SPRINKLER THRU-OUT | 169 S VETERAN AVEZone R1-1 | May 1, 2026 | IssuedExceeds 60-day law | 96 days | $44,000 |
| 24010-30001-04405Supplemental ref to pcis # 24010-30000-04405 to remove basement from scope of work and update structural inventory for overall information | 436 S DALEHURST AVEZone R1-1 | Mar 19, 2026 | Issued | 36 days | $501 |
| 26014-30000-01012ATTACHED ACCESSORY DWELLING UNIT ADDITION TO 2ND FLOOR OF (E) 2-STORY SINGLE FAMILY DWELLING WITH AN ATTACHED GARAGE PER LAMC 12.22 A.33(c) and (e). | 511-515 S WARNER AVEZone R1-1 | Mar 18, 2026 | IssuedExceeds 60-day law | 100 days | $200,000 |
| 25016-30001-37030Supplemental to PCIS#: 25016-30000-37030. Structural remodel and interior remodel of an (E) SFD. Convert portion of (E) SFD into a (N) Attached ADU per LAMC 12.22A.33(c) and(e). | 592-594 S MAPLETON DRZone RE40-1 | Mar 13, 2026 | IssuedExceeds 60-day law | 118 days | $80,000 |
| 26014-10000-00826eplan:ADDITION (7 ft x 16 ft) AND CONVERT (E) DETACHED GARGE( 17.42 ft x 20 ft) TO (N) A.D.U. ( 24.42 ft x 16 ft) PER STATE LAW GC 66323(a)(2) | 631 S WESTHOLME AVEZone R1-1 | Mar 5, 2026 | IssuedExceeds 60-day law | 155 days | $50,000 |
| 24016-20001-25314SUPPLEMENTAL TO 24016-20000-25314 TO ADD HALF BATHROOM TO DETACHED ADU AND UPDATE INVENTORY | 247 S THURSTON AVEZone R1-1 | Feb 18, 2026 | Issued | 56 days | $6,000 |
| 26016-10000-03685ePlan: Convert existing detached lath house and tool shed to ADU per LAMC 12.22 A.33(b)(1). | 1339 S CLUB VIEW DRZone R1V3 | Feb 9, 2026 | IssuedExceeds 60-day law | 74 days | $45,000 |
| 26014-10000-00397ePlan. Converstion and Addition of (E) Detached Garage to ADU Per | 1724 S ENSLEY AVEZone R1V3-O | Feb 3, 2026 | IssuedExceeds 60-day law | 87 days | $70,000 |
| 25016-70001-04776Supplemental ref: 25016-10000-04776 to revise T-24 and change to all electric building. | 236 S TAVISTOCK AVEZone R1-1 | Jan 8, 2026 | Permit Finaled | 0 days | — |
| 25010-20000-06269(N) 2-STORY SFD WITH ATTACHED TWO CAR GARAGE AND ACCESSORY DWELLING UNIT AS PER GC 66323(a)(1) , NFPA-13D FIRE SPRINKLERS THROUGHOUT, ALL WORK PER ENGINEERING | 821-823 S MALCOLM AVEZone R1-1 | Dec 17, 2025 | IssuedExceeds 60-day law | 99 days | $350,000 |
| 24010-10001-04093EPLAN. SUPPLEMENTAL PERMIT TO PERMIT #24010-10000-04093 TO REVISE T-24 FROM ALL ELECTRIC TO NATURAL GAS. NO OTHER CHANGES. | 842 S HILGARD AVEZone [Q]R4-1VL | Dec 3, 2025 | Permit Finaled | 14 days | $501 |
Check a Los Angeles building permit live
Search any permit number or street address in the City of Los Angeles Open Data registry. Your address stays in this browser tab and is never added to a link or stored.
60-day ADU shot-clock calculator & written notice
California Government Code § 66317 gives local permitting agencies 60 calendar days to ministerially approve or deny a complete Accessory Dwelling Unit application. Enter your application details below to calculate your statutory deadline and assemble a plain written status request for Westwood, Los Angeles.
- Submittal date
- November 23, 2026
- Day 45 check-in
- January 7, 2027
- Day 60 statutory deadline
- January 22, 2027
- Current status
- 60 days remaining in the 60-day window
Review written notice to LADBS Plan Check Supervisor
November 23, 2026
To: Plan Check Supervisor
Los Angeles Department of Building and Safety (LADBS)
201 N. Figueroa Street, Los Angeles, CA 90012
CC: California Department of Housing and Community Development (HCD) Housing Accountability Unit
Subject: Request for Ministerial ADU Review Status & Consolidated Corrections Under CA Gov. Code § 66317 — Permit #[PERMIT APPLICATION NUMBER]
Dear Plan Check Supervisor,
I am writing regarding Accessory Dwelling Unit (ADU) Permit Application #[PERMIT APPLICATION NUMBER] for [PROPERTY STREET ADDRESS, LOS ANGELES, CA], submitted on November 23, 2026.
Under California Government Code § 66317, the 60-day ministerial review window for a complete ADU application runs through January 22, 2027.
Pursuant to California Government Code § 66317, I respectfully request:
1. Immediate ministerial approval of this complete ADU application, OR
2. A single, complete, written set of objective code comments citing the exact code section for every remaining item so that all corrections can be resolved without serial plan-check cycles.
Please respond in writing with the current plan-check status, assigned plan checker, and next action date.
Sincerely,
[YOUR FULL NAME]
Permit Reference: #[PERMIT APPLICATION NUMBER]
Property Address: [PROPERTY STREET ADDRESS, LOS ANGELES, CA]
Election.org publishes official City of Los Angeles permit data and California statutory references for public accountability and citizen self-help. This draft is informational and is not legal representation; review every detail before sending.
Other Los Angeles Community Plan Areas
- West Adams – Baldwin Hills – Leimert, Los Angeles2,613 issued ADUs · 204 days average · 67% over 60 days
- South Los Angeles, Los Angeles2,603 issued ADUs · 217 days average · 72% over 60 days
- Northeast Los Angeles, Los Angeles2,334 issued ADUs · 229 days average · 69% over 60 days
- Wilshire, Los Angeles2,286 issued ADUs · 197 days average · 68% over 60 days
- Reseda – West Van Nuys, Los Angeles2,025 issued ADUs · 155 days average · 63% over 60 days
- Canoga Park – West Hills – Winnetka – Woodland Hills, Los Angeles2,021 issued ADUs · 155 days average · 60% over 60 days
Up: All Los Angeles permit timelines, Los Angeles officials, Local government
Sources & notes
Permit registryCity of Los Angeles Department of Building and Safety (LADBS) via City of Los Angeles Open Data
Open data endpointdata.lacity.org/resource/pi9x-tg5x.json
StatuteCalifornia Government Code § 66317 (60-day ministerial ADU review)
Data updatedNov 14, 2026